PRINCE2F PRINCE2 Processes Practice Question
A project is in the Initiating a Project process. Which activity would typically be performed during this process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Create the Project Plan and Stage Plans
Initiating a Project includes creating the Project Plan and Stage Plans. Appointing the Project Manager is done during Starting Up a Project. Producing the End Project Report is done during Closing a Project. Authorizing the next stage is done during Directing a Project.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Create the Project Plan and Stage Plans
Why this is correct
The Project Plan and Stage Plans are created during Initiating a Project as part of the PID.
- ✗
Authorize the next stage
Why it's wrong here
Authorizing stages is done by the Project Board during Directing a Project.
- ✗
Produce the End Project Report
Why it's wrong here
The End Project Report is produced during Closing a Project.
- ✗
Appoint the Project Manager
Why it's wrong here
The Project Manager is appointed during Starting Up a Project, not Initiating a Project.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.