PRINCE2F Business Case and Organizing Practice Question

A project is in its closing stage. The business case shows that all planned benefits have been realized. What should the project manager do?

⚠ Common exam trap

A common mix-up: candidates think closing the project immediately (Option D) is efficient, but PRINCE2 mandates a formal closure process that includes updating the Business Case and producing the End Project Report to ensure accountability and learning.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Update the Business Case with actual benefits and produce the End Project Report

In PRINCE2, the closing stage requires the project manager to formally confirm that all planned benefits have been realized. Updating the Business Case with actual benefits and producing the End Project Report is the correct action because it provides a formal record of benefit realization and lessons learned, which is essential for organizational learning and project closure. This aligns with the PRINCE2 principle of 'continued business justification' and the 'Closing a Project' process.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Start a new project to realize more benefits

    Why it's wrong here

    Not relevant.

  • Update the Business Case with actual benefits and produce the End Project Report

    Why this is correct

    Correct: finalize documentation.

  • Delete the project files

    Why it's wrong here

    Files must be archived, not deleted.

  • Close the project immediately

    Why it's wrong here

    Closing requires verification and documentation.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.