A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Raise an Exception Report to the Project Board
PRINCE2's management by exception requires escalation via an Exception Report when tolerances are forecast to be breached.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Continue and report in the next Highlight Report
Why it's wrong here
Must escalate immediately, not wait.
- ✗
Close the project
Why it's wrong here
Only Project Board can decide closure.
- ✓
Raise an Exception Report to the Project Board
Why this is correct
PM escalates via Exception Report for decision.
- ✗
Increase the project budget and continue
Why it's wrong here
PM cannot unilaterally change tolerances.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.