PRINCE2 ProcessesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Raise an Exception Report to the Project Board

PRINCE2's management by exception requires escalation via an Exception Report when tolerances are forecast to be breached.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Continue and report in the next Highlight Report

    Why it's wrong here

    Must escalate immediately, not wait.

  • Close the project

    Why it's wrong here

    Only Project Board can decide closure.

  • Raise an Exception Report to the Project Board

    Why this is correct

    PM escalates via Exception Report for decision.

  • Increase the project budget and continue

    Why it's wrong here

    PM cannot unilaterally change tolerances.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.