Courseiva
PRINCE2 PracticesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Raise an Exception Report to the Project Board

When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Close the project immediately

    Why it's wrong here

    Only the Project Board can decide to close the project.

  • Increase the project budget and continue

    Why it's wrong here

    The PM cannot unilaterally increase the budget.

  • Raise an Exception Report to the Project Board

    Why this is correct

    This is the correct response per management by exception.

  • Continue and report in the next Highlight Report

    Why it's wrong here

    Immediate escalation is required, not waiting for the next report.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.