Courseiva
PRINCE2 PracticesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Raise an Exception Report to the Project Board

When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Raise an Exception Report to the Project Board

    Why this is correct

    This is the correct response to a forecast tolerance breach.

  • Increase the project budget and continue

    Why it's wrong here

    The Project Manager cannot unilaterally increase the budget.

  • Continue and report in the next Highlight Report

    Why it's wrong here

    Continuing without escalation violates management by exception.

  • Close the project as the Business Case is no longer viable

    Why it's wrong here

    A cost breach does not automatically mean the Business Case is unviable.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.