What is the difference between a Request for Change (RFC) and an Off-specification?
An RFC proposes a change to an approved baseline; an Off-specification is a failure to meet a specified requirement.
Why this answer
An RFC is a proposal for a change that would deliver something not originally specified. An Off-specification is something that should have been provided but was not, i.e., a failure to meet a requirement.