Courseiva

CCNA Project Life Cycle Questions

11 of 161 questions · Page 3/3 · Project Life Cycle · Answers revealed

151
MCQmedium

A project manager is developing a network diagram and needs to represent an activity that can start only after its predecessor has finished. Which dependency type does this describe?

A.Finish-to-Start (FS)
B.Start-to-Start (SS)
C.Finish-to-Finish (FF)
D.Start-to-Finish (SF)
AnswerA

Correct: the successor starts only after the predecessor finishes.

Why this answer

Finish-to-Start (FS) is the most common dependency where the successor cannot start until the predecessor finishes.

152
MCQmedium

During project execution, a stakeholder requests a change to the project scope. What is the first step the project manager should take?

A.Inform the sponsor of the change
B.Submit a change request to the change control board
C.Implement the change immediately
D.Update the project baseline
AnswerB

The change request is the first formal step.

Why this answer

The first step in change control is to document the change request and submit it for impact analysis.

153
Multi-Selectmedium

A project manager is closing a project. Which THREE activities are part of the project closure process? (Select THREE).

Select 3 answers
A.Release project resources
B.Implement risk response strategies
C.Archive project documents
D.Create the Work Breakdown Structure
E.Obtain formal acceptance from the sponsor
AnswersA, C, E

Releasing resources is part of closing.

Why this answer

Project closure includes obtaining formal acceptance, archiving documents, and releasing resources. Risk response strategies are part of execution, and creating the WBS is part of planning.

154
MCQeasy

During the initiating phase of a project, a project charter is created. Which of the following is typically included in a project charter?

A.Project purpose and high-level scope
B.Detailed work breakdown structure
C.Risk register with identified risks
D.Earned value metrics
AnswerA

The project charter defines the high-level scope and purpose of the project.

Why this answer

The project charter includes the project purpose, objectives, high-level scope, budget, schedule, assumptions, constraints, and the authority of the project manager.

155
MCQmedium

A project manager is evaluating risk responses. For a risk with high probability and high impact, which risk response strategy is most appropriate to eliminate the threat?

A.Accept
B.Mitigate
C.Transfer
D.Avoid
AnswerD

Avoidance changes the project plan to completely eliminate the risk.

Why this answer

Avoidance is the only strategy that completely eliminates the threat by changing the project plan to avoid the risk. Transfer shifts liability, mitigate reduces impact/probability, and acceptance acknowledges the risk without action.

156
MCQmedium

A project team is experiencing conflicts and power struggles among members. According to Tuckman's stages of group development, which stage is the team likely in?

A.Performing
B.Storming
C.Forming
D.Norming
AnswerB

Storming involves conflict, power struggles, and resistance to group influence.

Why this answer

In the storming stage, team members may have differing opinions, leading to conflicts and power struggles as they assert themselves.

157
Multi-Selecteasy

Which TWO of the following are outputs of the monitoring and controlling process group? (Select two.)

Select 2 answers
A.Project charter
B.Risk register
C.Work breakdown structure
D.Performance reports
E.Change requests
AnswersD, E

Performance reports are outputs of monitoring and controlling.

Why this answer

Performance reports and change requests are typical outputs of monitoring and controlling. The project charter is an output of initiating, and the risk register is an output of planning.

158
MCQeasy

A project manager is preparing a procurement document that asks vendors to provide a price for a specific product. Which type of document is this?

A.Request for quotation (RFQ)
B.Request for proposal (RFP)
C.Request for information (RFI)
D.Statement of work (SOW)
AnswerA

RFQ is used to request a price for a specific product.

Why this answer

A request for quotation (RFQ) is used to obtain a price for a specific item.

159
Multi-Selecteasy

During project closing, a project manager must complete several activities. Which TWO are appropriate for project closure?

Select 2 answers
A.Create the project charter
B.Update the risk register
C.Archive project documents
D.Develop the project schedule
E.Obtain formal acceptance of deliverables from the sponsor
AnswersC, E

Correct. Archiving documents is part of closing.

Why this answer

Project closure includes formal acceptance from the sponsor/customer and archiving project documents. Releasing resources and lessons learned are also closure activities, but the question asks for TWO from the options.

160
MCQmedium

A vendor is hired to provide a service with a fixed price of $100,000, regardless of actual costs incurred. Which contract type is this?

A.Fixed-price
B.Time and Materials (T&M)
C.Cost-reimbursable
D.Cost-plus
AnswerA

Correct: fixed-price has a set price.

Why this answer

A fixed-price contract has a predetermined price that does not change based on the seller's cost performance.

161
Multi-Selecthard

A project manager is planning risk responses for identified risks. Which THREE are valid risk response strategies?

Select 3 answers
A.Ignore
B.Enhance
C.Avoid
D.Mitigate
E.Transfer
AnswersC, D, E

Correct: Avoid involves eliminating the risk.

Why this answer

The main risk response strategies are Avoid, Transfer, Mitigate, and Accept. Enhance is for opportunities, not threats.

← PreviousPage 3 of 3 · 161 questions total

Ready to test yourself?

Try a timed practice session using only Project Life Cycle questions.