Which TWO of the following are outputs of the monitoring and controlling process group? (Select two.)

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Performance reports

Performance reports and change requests are typical outputs of monitoring and controlling. The project charter is an output of initiating, and the risk register is an output of planning.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project charter

    Why it's wrong here

    Project charter is an output of initiating.

  • Risk register

    Why it's wrong here

    Risk register is an output of planning.

  • Work breakdown structure

    Why it's wrong here

    WBS is an output of planning.

  • Performance reports

    Why this is correct

    Performance reports are outputs of monitoring and controlling.

  • Change requests

    Why this is correct

    Change requests are outputs of monitoring and controlling.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.