PK0-005 Project Life Cycle Practice Question
Which TWO of the following are outputs of the monitoring and controlling process group? (Select two.)
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Performance reports
Performance reports and change requests are typical outputs of monitoring and controlling. The project charter is an output of initiating, and the risk register is an output of planning.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project charter
Why it's wrong here
Project charter is an output of initiating.
- ✗
Risk register
Why it's wrong here
Risk register is an output of planning.
- ✗
Work breakdown structure
Why it's wrong here
WBS is an output of planning.
- ✓
Performance reports
Why this is correct
Performance reports are outputs of monitoring and controlling.
- ✓
Change requests
Why this is correct
Change requests are outputs of monitoring and controlling.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.