Question 495 of 980
mediumMultiple SelectObjective-mapped
Documents Created During Project Planning Phase
Which TWO documents are typically created during the project planning phase?
Quick Answer
The answer is the project schedule and the risk register. These two documents are typically created during the project planning phase because planning is where the project’s execution roadmap is formally defined. The project schedule sequences tasks, assigns durations, and sets milestones, while the risk register identifies, assesses, and documents potential risks with their probability, impact, and response strategies. On the CompTIA Project+ PK0-005 exam, this distinction tests your understanding of the planning process group versus initiation or execution; a common trap is confusing the project charter (an initiation document) with the risk register. To remember, think of planning as the phase where you build the “how” and the “what if”—the schedule maps the work, and the risk register prepares for surprises. A simple memory tip: “Plan the work, then plan the what-ifs.”
⚠ Common exam trap
Many exam-takers confuse the project charter (initiating) with planning documents, or mistaking lessons learned (closing) and issue log (executing/monitoring) as planning outputs, when only the risk register and project schedule are formally created during the planning phase.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Risk register
The risk register is created during the project planning phase to identify, assess, and document potential risks that could impact the project. It includes risk descriptions, probability, impact, and response strategies, forming a key input for risk management throughout the project lifecycle.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Risk register
Why this is correct
Risk register is created during planning.
- ✗
Lessons learned
Why it's wrong here
Lessons learned are documented during closing.
- ✗
Project charter
Why it's wrong here
Project charter is created during initiation, not planning.
- ✓
Project schedule
Why this is correct
Project schedule is developed during planning.
- ✗
Issue log
Why it's wrong here
Issue log is used during execution, not planning.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
1 more way this is tested on PK0-005
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Which TWO documents are typically created during the planning process group?
medium- A.Change request
- B.Issue log
- ✓ C.Work breakdown structure
- ✓ D.Risk register
- E.Project charter
Why C: The Work Breakdown Structure (WBS) is a key planning document that decomposes the project scope into manageable work packages. It is created during the planning process group to define and organize the total work required, serving as a foundation for cost estimation, scheduling, and resource allocation.
Last reviewed: Jun 11, 2026
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.