In a network diagram, the critical path is the longest path through the project. What does it determine?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The shortest possible project duration

The critical path determines the shortest possible project duration; any delay on the critical path delays the project.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The project's budget

    Why it's wrong here

    The critical path is about time, not cost.

  • The shortest possible project duration

    Why this is correct

    Correct. The critical path gives the minimum time to complete the project.

  • The resource allocation

    Why it's wrong here

    Resource allocation is separate from the critical path.

  • The project's total float

    Why it's wrong here

    Total float is the amount of time a task can be delayed without affecting the project, but the critical path has zero float.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.