A project manager is analyzing project performance using earned value management. Which THREE metrics are used to calculate the estimate at completion (EAC)?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Actual cost (AC)

EAC can be calculated using BAC/CPI, or AC + ETC, but ETC often uses CPI. So BAC, AC, and CPI are directly involved. EV is not directly in the formula.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Actual cost (AC)

    Why this is correct

    AC is used in EAC = AC + (BAC - EV)/CPI etc.

  • Earned value (EV)

    Why it's wrong here

    EV is not directly used in EAC formulas, though it is used to calculate CPI.

  • Planned value (PV)

    Why it's wrong here

    PV is not used in EAC calculations.

  • Budget at completion (BAC)

    Why this is correct

    BAC is used in EAC = BAC/CPI.

  • Cost performance index (CPI)

    Why this is correct

    CPI is used to project future performance.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.