Predictive Plan-Based MethodologiesmediumMultiple ChoiceObjective-mapped

CAPM Predictive Plan-Based Methodologies Practice Question

Exhibit

Refer to the exhibit.
```json
{
  "risk_id": "R001",
  "description": "Server hardware failure",
  "probability": "0.8",
  "impact": "High",
  "cost_impact_usd": 50000,
  "response": "Mitigate: Redundant servers"
}
```

Using the risk register entry shown, what is the expected monetary value (EMV) of this risk?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

$40,000

$40,000. EMV = Probability * Impact = 0.8 * $50,000 = $40,000. Option A ($10,000) incorrectly uses a probability of 0.2. Option B ($50,000) uses the impact alone without probability. Option C ($80,000) is likely from multiplying 0.8 by $100,000 or a calculation error.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • $10,000

    Why it's wrong here

    This would be the EMV if probability were 0.2.

  • $50,000

    Why it's wrong here

    This is the impact without considering probability.

  • $80,000

    Why it's wrong here

    This would be the EMV if probability were 1.6, which is impossible.

  • $40,000

    Why this is correct

    0.8 * $50,000 = $40,000 correct EMV.

About these practice questions

Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.