Requirements Traceability Matrix: Linking Requirements to Test Cases
Exhibit
Refer to the exhibit. ``` Requirements Traceability Matrix (RTM) ID | Requirement Description | Source | Design | Test Case | Status R001 | User login with SSO | Stakeholder A | D001 | TC001 | Approved R002 | Dashboard with charts | Stakeholder B | D002 | TC002 | In Review R003 | Export to PDF | Stakeholder C | D003 | TC003 | Approved ```
Based on the exhibit, which requirement is not yet linked to a test case?
Quick Answer
The answer is None of the above because the requirements traceability matrix (RTM) in the exhibit shows that every listed requirement—R001, R002, and R003—has at least one test case linked to it, leaving no requirement unlinked. This scenario tests your understanding of the RTM’s core function: ensuring bidirectional traceability between requirements and test cases, which validates that all project scope items are covered by testing. On the Certified Associate in Project Management (CAPM) exam, this concept appears in the scope management knowledge area, often as a trick where a candidate might overlook a linked requirement or assume a missing link exists. A common trap is misreading the exhibit and thinking a requirement is unlinked when it actually has a test case association elsewhere in the matrix. For a quick memory tip, remember “RTM = All Reqs Tested,” meaning every requirement must have at least one test case link to confirm coverage.
⚠ Common exam trap
Test-takers frequently assume a requirement is unlinked if they misread the matrix or overlook a connection arrow, but the exhibit clearly shows each requirement has a corresponding test case.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
None of the above
The exhibit shows that requirements R001, R002, and R003 are each linked to at least one test case. Since all listed requirements already have test case associations, the correct answer is 'None of the above' — no requirement remains unlinked.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
None of the above
Why this is correct
All requirements have associated test cases.
- ✗
R001
Why it's wrong here
R001 is linked to TC001.
- ✗
R002
Why it's wrong here
R002 is linked to TC002.
- ✗
R003
Why it's wrong here
R003 is linked to TC003.
Go deeper
Related to this question
About these practice questions
One of 487 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
1 more way this is tested on CAPM
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Which tool is used to visually represent the relationships between requirements and other project artifacts?
medium- A.WBS
- ✓ B.RTM
- C.Network diagram
- D.Gantt chart
Why B: The Requirements Traceability Matrix (RTM) is a grid that links requirements to their origin, design, development, and testing artifacts.
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.