Courseiva
Predictive Plan-Based MethodologiesmediumMultiple ChoiceObjective-mapped

Risk Transfer Strategy: Performance Bonds for High-Impact Risks

A manufacturing company is planning to install a new production line using a predictive project management approach. The project has a fixed price contract with a supplier for a critical machine. During the plan risk management process, the project manager identifies a risk that the key supplier might declare bankruptcy before delivering the machine. This risk has a high probability due to the supplier's financial instability, and a high impact because the machine is on the critical path and has a long lead time. The project manager must decide on a risk response strategy that will minimize the potential impact on the project. The team suggests several options.

Quick Answer

The correct answer is to transfer the risk by requiring the supplier to obtain a performance bond. This risk transfer strategy is the most appropriate for a high-impact, high-probability threat because it shifts the financial burden of the supplier’s potential bankruptcy to a third-party surety, ensuring the project is compensated if the critical machine is not delivered. On the Certified Associate in Project Management CAPM exam, this scenario tests your ability to apply risk response strategies within a predictive project management framework, specifically distinguishing transfer from mitigation or avoidance. A common trap is confusing transfer with mitigation—remember, transfer does not eliminate the risk but assigns the financial consequences to another party, while mitigation would involve actions like sourcing a backup supplier. For a memory tip, think of a performance bond as an insurance policy for the project’s critical path: if the supplier fails, the bond pays out, keeping your schedule intact.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Transfer the risk by requiring the supplier to obtain a performance bond.

Transferring the risk via a performance bond is the most appropriate response for this high-probability, high-impact risk. A performance bond guarantees that the supplier will fulfill its obligations; if the supplier defaults, the bonding company covers the financial loss, thereby protecting the project. This minimizes the potential impact without requiring a change in machine or relying on a backup supplier that may not meet lead time requirements. Option A (avoid) might be impractical or costly; option B (mitigate) does not fully address the risk; option D (accept) is insufficient for a high-priority risk. Therefore, option C is correct.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Avoid the risk by selecting a different machine that is available from multiple suppliers.

    Why it's wrong here

    Avoidance may not be feasible as the machine is specified in the contract and changing may cause delays and cost overruns.

  • Mitigate the risk by establishing a backup supplier.

    Why it's wrong here

    While mitigation is good, establishing a backup supplier may not be possible pending contract termination with the original supplier. Transfer is more direct.

  • Transfer the risk by requiring the supplier to obtain a performance bond.

    Why this is correct

    A performance bond transfers the financial risk to a third party, protecting the project.

  • Accept the risk and document it in the risk register.

    Why it's wrong here

    Acceptance is passive and not appropriate for high-probability high-impact risks.

About these practice questions

One of 487 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on CAPM

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. A project manager is creating a risk response plan for a predictive construction project. One risk has a high probability and high impact. The team decides to purchase insurance to cover potential losses. Which risk response strategy is being used?

hard
  • A.Avoid
  • B.Accept
  • C.Mitigate
  • D.Transfer

Why D: Purchasing insurance transfers the financial impact of the risk to a third party (the insurer), which is the definition of the transfer strategy. Option A (Avoid) is incorrect because avoidance eliminates the risk entirely, e.g., by not performing the activity; insurance does not eliminate the risk. Option B (Accept) is incorrect because acceptance means acknowledging the risk and taking no proactive action, often setting aside a contingency reserve; purchasing insurance is an active response. Option C (Mitigate) is incorrect because mitigation reduces the probability or impact of the risk; insurance does not reduce the likelihood or severity of the loss, it only shifts the financial burden.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.