CAPM Business Analysis Frameworks Practice Question

Match each earned value management term to its formula.

Drag a concept onto its matching description — or click a concept then click the description.

Concepts
Matches

Budgeted cost of work scheduled

Budgeted cost of work performed

Actual cost incurred for work done

EV minus AC

EV minus PV

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

PV: Budgeted cost of work scheduled

EVM metrics: PV and EV are budgeted costs, AC is actual cost. Variances: SV = EV-PV, CV = EV-AC. Indices: SPI = EV/PV, CPI = EV/AC.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • PV: Budgeted cost of work scheduled

    Why this is correct

    Correct: PV is the budgeted cost for work scheduled.

  • EV: Actual cost of work performed

    Why it's wrong here

    Incorrect: This describes AC, not EV.

  • AC: Actual cost of work performed

    Why this is correct

    Correct: AC is the actual cost incurred.

  • SV: EV - AC

    Why it's wrong here

    Incorrect: This is the formula for CV, not SV.

  • CV: EV - AC

    Why this is correct

    Correct: CV is EV minus AC.

  • SPI: AC / EV

    Why it's wrong here

    Incorrect: SPI is EV divided by PV, not AC divided by EV.

About these practice questions

One of 487 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.