CAPM Predictive Plan-Based Methodologies Practice Question
Exhibit
Refer to the exhibit.
```json
{
"WBS": {
"1.0 Project": {
"1.1 Planning": {
"1.1.1 Requirements",
"1.1.2 Design"
},
"1.2 Execution": {
"1.2.1 Development",
"1.2.2 Testing"
},
"1.3 Closure": {
"1.3.1 Deployment",
"1.3.2 Handover"
}
}
}
}
```How many work packages are at WBS level 2 (the second level) in this exhibit?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
3
Level 1 is '1.0 Project'. Level 2 consists of '1.1 Planning', '1.2 Execution', and '1.3 Closure' — that's three work packages. Option B incorrectly counts four, option C counts two, and option D counts six (the leaf nodes).
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
3
Why this is correct
The three decomposition elements at level 2 are Planning, Execution, and Closure.
- ✗
4
Why it's wrong here
This would count the sub-elements at level 3, not level 2.
- ✗
2
Why it's wrong here
There are more than two elements at level 2.
- ✗
6
Why it's wrong here
This counts all leaf work packages, which are at level 3, not level 2.
Go deeper
Related to this question
About these practice questions
This CAPM question is part of Courseiva's 487-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.