Predictive Plan-Based MethodologieseasyMultiple ChoiceObjective-mapped

CAPM Predictive Plan-Based Methodologies Practice Question

During the execution phase of a software development project, the team discovers a critical bug that requires an immediate fix. The project manager uses the contingency reserve to address this. Which plan-based process is being applied?

⚠ Common exam trap

A common mix-up: candidates confuse using a contingency reserve with simply executing work (Direct and Manage Project Work) or monitoring performance (Monitor and Control Project Work), failing to recognize that any use of baseline reserves must go through formal change control to maintain the integrity of the project baselines.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Perform Integrated Change Control

D is correct because using the contingency reserve to address a critical bug requires a formal change request to authorize the release of funds from the reserve. This aligns with the Perform Integrated Change Control process, which evaluates, approves, and manages changes to project baselines, including the cost baseline. The project manager must submit a change request, which is then reviewed by the Change Control Board (CCB) before the contingency reserve can be applied.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Direct and Manage Project Work

    Why it's wrong here

    This process executes the work defined in the plan, not manage changes.

  • Monitor and Control Project Work

    Why it's wrong here

    This process tracks progress and performance, but changes are handled by change control.

  • Close Project or Phase

    Why it's wrong here

    This process finalizes project activities, not handle changes during execution.

  • Perform Integrated Change Control

    Why this is correct

    This process manages changes to baselines, including using contingency reserves.

About these practice questions

This CAPM question is part of Courseiva's 487-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.