Question 461 of 503
Predictive Plan-Based MethodologieseasyMultiple ChoiceObjective-mapped

CAPM Predictive Plan-Based Methodologies Practice Question

This CAPM practice question tests your understanding of predictive plan-based methodologies. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

During the execution phase of a software development project, the team discovers a critical bug that requires an immediate fix. The project manager uses the contingency reserve to address this. Which plan-based process is being applied?

Question 1easymultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Perform Integrated Change Control

D is correct because using the contingency reserve to address a critical bug requires a formal change request to authorize the release of funds from the reserve. This aligns with the Perform Integrated Change Control process, which evaluates, approves, and manages changes to project baselines, including the cost baseline. The project manager must submit a change request, which is then reviewed by the Change Control Board (CCB) before the contingency reserve can be applied.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Direct and Manage Project Work

    Why it's wrong here

    This process executes the work defined in the plan, not manage changes.

  • Monitor and Control Project Work

    Why it's wrong here

    This process tracks progress and performance, but changes are handled by change control.

  • Close Project or Phase

    Why it's wrong here

    This process finalizes project activities, not handle changes during execution.

  • Perform Integrated Change Control

    Why this is correct

    This process manages changes to baselines, including using contingency reserves.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often confuse using a contingency reserve with simply executing work (Direct and Manage Project Work) or monitoring performance (Monitor and Control Project Work), failing to recognize that any use of baseline reserves must go through formal change control to maintain the integrity of the project baselines.

Detailed technical explanation

How to think about this question

Contingency reserves are time or cost buffers included in the project baseline to address identified risks (known unknowns). Using them requires a change request because it alters the cost baseline, which is a controlled document under Perform Integrated Change Control. In practice, the project manager must document the bug fix effort, estimate the cost impact, and submit a change request to the CCB; only after approval can the reserve be released and the work executed.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the CAPM exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related CAPM practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free CAPM practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this CAPM question test?

Predictive Plan-Based Methodologies — This question tests Predictive Plan-Based Methodologies — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Perform Integrated Change Control — D is correct because using the contingency reserve to address a critical bug requires a formal change request to authorize the release of funds from the reserve. This aligns with the Perform Integrated Change Control process, which evaluates, approves, and manages changes to project baselines, including the cost baseline. The project manager must submit a change request, which is then reviewed by the Change Control Board (CCB) before the contingency reserve can be applied.

What should I do if I get this CAPM question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.