Courseiva
Business Analysis FrameworksmediumDrag & DropObjective-mapped

CAPM Business Analysis Frameworks Practice Question

Drag and drop the steps for closing a project phase or project in the correct order.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4
5Step 5

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

1. Verify deliverables are complete, 2. Obtain formal acceptance, 3. Release resources, 4. Close contracts, 5. Archive documents

Closing involves verifying work, obtaining acceptance, releasing resources, closing contracts, and archiving documents.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 1. Verify deliverables are complete, 2. Obtain formal acceptance, 3. Release resources, 4. Close contracts, 5. Archive documents

    Why this is correct

    This order follows the PMBOK Guide's recommended sequence for closing a project or phase: first confirm all work is done, get sign-off, free up resources, finalize contractual obligations, and then store project records.

  • 1. Obtain formal acceptance, 2. Verify deliverables are complete, 3. Release resources, 4. Close contracts, 5. Archive documents

    Why it's wrong here

    This is incorrect because formal acceptance should occur after verification, not before. You cannot obtain sign-off on incomplete or unverified deliverables.

  • 1. Release resources, 2. Close contracts, 3. Verify deliverables, 4. Obtain formal acceptance, 5. Archive documents

    Why it's wrong here

    This is incorrect because releasing resources and closing contracts should happen after the deliverables have been verified and accepted. Doing these steps prematurely can disrupt project closure.

  • 1. Archive documents, 2. Close contracts, 3. Release resources, 4. Verify deliverables, 5. Obtain formal acceptance

    Why it's wrong here

    This is incorrect because archiving should be the last step, after all other closure activities are completed. Verifying and obtaining acceptance must occur before releasing resources and closing contracts.

About these practice questions

Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.