CAPM Predictive Plan-Based Methodologies Practice Question
Exhibit
Refer to the exhibit. Exhibit: ``` Task ID | Predecessor | Duration (days) A | None | 3 B | A | 4 C | A | 2 D | B, C | 5 E | D | 2 F | D | 3 G | E, F | 1 ```
Based on the exhibit, what is the critical path duration?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
15 days
The critical path is the longest path through the network. Path A-B-D-E-G = 3+4+5+2+1 = 15 days. Path A-C-D-F-G = 3+2+5+3+1 = 14 days. Therefore, the critical path duration is 15 days. Options B, C, and D are incorrect because they do not represent the longest path duration.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
15 days
Why this is correct
The critical path is A-B-D-E-G with 15 days.
- ✗
16 days
Why it's wrong here
No path sums to 16 days.
- ✗
14 days
Why it's wrong here
This is the duration of path A-C-D-F-G, not the longest.
- ✗
13 days
Why it's wrong here
No path sums to 13 days.
Go deeper
Related to this question
About these practice questions
One of 487 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.