Courseiva
Predictive Plan-Based MethodologiesmediumMultiple ChoiceObjective-mapped

CAPM Predictive Plan-Based Methodologies Practice Question

A project manager identifies a risk that could cause a 10-day delay. The probability of occurrence is 30%. What is the expected monetary value (EMV) of this risk?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

3 days

EMV is calculated as Probability × Impact. Here, 0.3 × 10 days = 3 days. EMV is used to quantify risk in monetary terms, but in this case impact is in days.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 3 days

    Why this is correct

    EMV = 0.3 × 10 = 3 days.

  • 10 days

    Why it's wrong here

    This is the impact, not the EMV.

  • 0.3 days

    Why it's wrong here

    This is just the probability, not multiplied by impact.

  • 30 days

    Why it's wrong here

    This is the probability multiplied incorrectly.

About these practice questions

One of 487 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.