Match each scenario symptom to the correct Agile mechanic: WIP limits for Kanban bottlenecks, the Sprint Retrospective for process improvement, velocity divided into remaining points for release forecasting, and backlog reprioritization plus short iterations for changing requirements. The key skill is selecting the single best-fitting practice, not the most familiar one.
Start practicing
Agile Frameworks and Methodologies — choose a session length
Free · No account required
Domain overview
This domain covers Agile frameworks and methodologies as tested by CAPM: Kanban flow practices, Scrum events and artifacts, velocity-based release planning, and how Agile teams absorb changing requirements. Questions are scenario-based, asking you to pick the practice or event that best fits a described problem, so you must match the symptom to the correct framework mechanic.
Exam objectives
Kanban: limiting work in progress and pulling work to relieve stage bottlenecks
Scrum events: Sprint Retrospective for inspecting and adapting team process
Scrum artifacts and roles: Product Backlog, Product Owner, velocity-based release forecasting
Agile requirement change handling: short iterations, backlog refinement, and reprioritization
Choosing a Scrum event like Sprint Review or Daily Scrum when the scenario asks specifically about improving process, which is the Retrospective's purpose.
Treating Kanban as having timeboxed Sprints or velocity; Kanban uses continuous flow and WIP limits, not story-point velocity.
Assuming changing requirements should be frozen or handled by a change control board rather than embraced through backlog reprioritization.
Click any question to see the full explanation and answer options, or start a focused practice session above.
A team is using Scrum and notices that the Product Owner frequently changes priorities during the Sprint, causing the team to rework tasks. What should the Scrum Master do first?
2In Kanban, the team is experiencing frequent bottlenecks at the testing stage. Which practice should they adopt to improve flow?
3A distributed Scrum team is having difficulty with communication across time zones. The Daily Scrum is scheduled at 9 AM in the US, which is midnight in India. What is the best approach to resolve this?
4During Sprint Planning, the Product Owner proposes a user story that is too large to fit in one Sprint. What should the team do?
5A team is new to Agile and wants to implement a framework that emphasizes iterative development, time-boxed iterations, and a prioritized backlog. Which framework should they adopt?
6Which THREE of the following are core values of the Agile Manifesto?
7During Sprint Planning, the team realizes the password reset story involves a third-party email service that has not been integrated yet. The team has no experience with that service. What is the best action?
8The team notices that work is piling up in the Testing column. The WIP limit for Testing is 3, but currently there are 5 items. What should the team do first?
9A startup is adopting Scrum for the first time. During the Sprint Review, stakeholders request many changes to the product increment. What is the best way for the Scrum Master to handle this?
10In a Kanban system, the team notices that work items are spending too much time in the 'In Progress' column. Which practice should the team adopt to improve flow?
11An XP team is practicing pair programming. A new developer feels uncomfortable because the partner frequently corrects their code. What is the best way to foster a positive pairing experience?
12Which TWO are Scrum artifacts? (Choose two.)
13Which THREE are principles of the Agile Manifesto? (Choose three.)
14A software development team is transitioning from a plan-driven approach to Scrum. The Product Owner is enthusiastic but struggles to break down the product backlog into small, independent items. The team frequently encounters dependencies between user stories, causing delays in sprints. What is the best course of action for the Scrum Master to address this issue?
15Drag and drop the steps for managing project quality in the correct order.
16A project team is adopting Kanban. They currently have a cycle time of 10 days and a throughput of 5 items per week. The team wants to improve predictability. Which action would most directly help?
17An organization is scaling Scrum across multiple teams. They have dependencies between teams that cause delays. What is the most appropriate framework to address this?
18In Extreme Programming (XP), which practice involves integrating and testing the entire system multiple times per day?
19A Scrum Master notices that the development team is not self-organizing and often waits for instructions. What is the best coaching approach?
20A team using Scrum has a velocity of 30 story points per Sprint. The Product Owner wants to plan for the next release with 150 story points of work remaining. The team is stable. Which release planning approach aligns with agile principles?
21Which is an effective way to prioritize user stories in a product backlog?
22In a hybrid agile project, the team uses Scrum for development but the organization requires a detailed upfront plan. How can the team comply while staying agile?
23A team is struggling with frequent requirement changes during a Sprint. The Product Owner keeps adding new items. What should the Scrum Master do?
24Which TWO practices are part of the Scrum framework?
25Which THREE activities are part of the Sprint Planning meeting in Scrum?
26Which THREE principles are common to multiple agile methodologies?
27Refer to the exhibit. What issue does the Kanban board reveal?
28At the daily stand-up meeting, a team member consistently arrives 10 minutes late, causing the meeting to start late. What is the best agile practice to address this?
29A company transitioning from a waterfall to a Scrum framework wants to ensure continuous improvement. Which Scrum event is specifically designed for inspecting and adapting the process?
30In a Kanban system, what is the primary purpose of limiting Work in Progress (WIP)?
31During Sprint Planning, the Development Team realizes that the total effort for the selected Product Backlog items exceeds their historical velocity. What should the team do?
32A Product Owner frequently misses backlog refinement sessions, leaving user stories vague. The Development Team is struggling to estimate and plan Sprints. What fundamental Scrum role is being neglected?
33A Scrum team has a stable velocity of 30 story points per sprint. The Product Owner requests that the team deliver 50 story points in the next sprint to meet a market deadline. What is the best course of action for the Scrum Master?
34A geographically distributed agile team using Scrum is experiencing frequent integration issues and delays caused by incompatible code changes. Which Extreme Programming (XP) practice would best address this problem?
35A Scrum Master observes that the Development Team consistently overcommits during Sprint Planning and often fails to deliver all committed items by the Sprint Review. What should the Scrum Master do?
36Which TWO activities are considered part of Product Backlog refinement? (Select TWO)
37Which TWO statements about the Sprint Backlog are true? (Select TWO)
38Which THREE roles are defined in the Scrum Guide? (Select THREE)
39A team using Scrum consistently fails to complete all planned work in a sprint. What should the Scrum Master do first?
40Refer to the exhibit. The team's velocity is 30 points per sprint, and they have already committed to stories totaling 22 points. What is the team's remaining capacity for this sprint?
41Refer to the exhibit. The team wants to pull a new item into In Progress. What should they do first?
42Which TWO practices are characteristic of Extreme Programming (XP)? (Choose two)
43A team is transitioning to Kanban. Which TWO principles should they adopt? (Choose two)
44Which THREE are events in the Scrum framework? (Choose three)
45What is the primary role of the Product Owner in Scrum?
46A team is working on a project with high uncertainty. Which agile framework is most suitable?
47In Kanban, what is the primary purpose of limiting Work in Progress (WIP)?
48Which of the following is a key benefit of using a Kanban board?
49In Scrum, what is the purpose of the Sprint Retrospective?
50An Agile team consistently completes only about 70% of the planned work each sprint. Which action is most likely to improve the team's ability to meet commitments?
51Which practice is a key component of Extreme Programming (XP)?
52An Agile team is experiencing frequent changes in requirements from stakeholders. Which approach best enables the team to adapt while maintaining productivity?
53A Kanban team notices that cycle time is increasing despite stable demand. Which action is most likely to reduce cycle time?
54Which TWO are benefits of self-organizing teams?
55Which THREE are formal Scrum ceremonies (events) as defined in the Scrum Guide?
56Which TWO are core practices of Extreme Programming (XP)?
57A company uses Scrum with two-week sprints. The team's velocity is 30 story points per sprint, and they have a well-refined product backlog. However, stakeholders frequently introduce urgent, high-priority requests mid-sprint, which the Product Owner accepts because of stakeholder pressure. As a result, the team is overcommitted each sprint, often leaving 40% of planned work incomplete. The Product Owner is frustrated because promised features are delayed, and the team feels demotivated due to constant interruptions. The Scrum Master has been asked to intervene. What is the best course of action for the Scrum Master?
58A software development team has been using a feature branch workflow with long-lived branches. They frequently experience merge conflicts and integration delays. The team wants to adopt a more agile approach to reduce these issues. Which practice should the team adopt?
59During a Scrum sprint, the development team discovers that a critical dependency on another team's API cannot be resolved until the next sprint. The product owner insists on delivering the current sprint goal without adjusting scope. The team is struggling to meet the definition of done. What should the Scrum Master do first?
60A product owner is writing user stories for a new feature. Which of the following is a best practice for ensuring the stories are well-formed?
61An organization is transitioning from a traditional project management approach to Scrum. The project manager has been reassigned as a Scrum Master but continues to assign tasks to team members and track individual progress. The team is becoming demotivated. What should the Scrum Master do differently?
62During a sprint retrospective, the team identifies that they often spend too much time in daily stand-up meetings. What is the recommended timebox for the daily Scrum in Scrum?
63Which TWO statements correctly describe characteristics of the Kanban method?
64According to the Scrum Guide, which THREE of the following are Scrum events?
65Which TWO are benefits of using an iterative approach in agile projects?
66A financial services company is adopting Scrum for a critical compliance project. The team has six developers, one product owner, and one Scrum Master. After three sprints, the product owner is frustrated because the team has only delivered 40% of the planned features. The team says they are working full capacity but keep getting interrupted by urgent production support requests from the operations team. The Scrum Master notices that the team’s velocity is dropping each sprint. The product owner insists on increasing the sprint length from two weeks to four weeks to allow more time for delivery. However, the compliance deadline is fixed. The Scrum Master must recommend a course of action. What should the Scrum Master do?
67A startup is using Scrum to develop a mobile app. The product owner has a clear vision and has written detailed user stories for the first release. During sprint planning, the development team estimates that they can complete 40 story points per sprint. However, after two sprints, the team has only completed 30 points per sprint. The product owner is concerned and wants to hold the team accountable. The team says that the estimates were optimistic and that they are still learning the technology. The Scrum Master notices that the team is not using pair programming or test-driven development (TDD) as originally planned. The product owner suggests reducing scope for the next sprint to match the team’s actual velocity. The Scrum Master must decide the best way to proceed. What should the Scrum Master do?
68A newly formed agile team is about to start their first sprint. The product owner has a well-groomed backlog and the team has done relative sizing using planning poker. The team is excited but unsure about the process. They ask the Scrum Master what the primary goal of the first iteration should be. The Scrum Master should explain that the most important goal of the first sprint is to deliver a potentially releasable increment of the product. However, some team members are worried they may not be able to deliver enough due to team formation and learning the codebase. The product owner wants to see a visible outcome. What should the Scrum Master recommend as the primary focus for the first sprint?
69During a sprint review, the team demonstrates a new feature to stakeholders. One stakeholder says, 'This isn't what we wanted. We need a completely different approach.' The product owner is upset because the feature took two weeks to build. The team is frustrated because they followed the product owner's specifications exactly. The Scrum Master observes that the product owner did not involve stakeholders during the sprint and based the user stories on assumptions. The product owner wants to add the rework to the next sprint. However, the team's capacity is already full. The Scrum Master needs to help the team and product owner recover. What should the Scrum Master do first?
70An agile team is using a burndown chart for the first time. After six days of a two-week sprint, the burndown chart shows that the remaining work has increased compared to the previous day. The team is confused. They had completed several tasks, but new tasks were added to the sprint backlog after the sprint started. The product owner says the additions were urgent and necessary. The development team is frustrated because they feel the sprint goal is at risk. The Scrum Master must address this situation. What should the Scrum Master do?
71A Scrum team is preparing for its Sprint Review. The Product Owner wants to know which artifacts the team should present to stakeholders to demonstrate the completed work. What is the most appropriate focus for the Sprint Review?
72An agile team has been running two-week Sprints for several months. During each Sprint Review, stakeholders provide feedback, but the team notices that the same concerns keep resurfacing and no one owns follow-up actions. The Scrum Master wants to ensure that the team inspects how it is working and adapts its process. Which Scrum event should the Scrum Master focus on to address this?
73An agile team is adopting Extreme Programming (XP). A developer asks how the practice of continuous integration differs from simply building the software nightly. Which statement best describes the XP practice of continuous integration?
74A Scrum team is halfway through a two-week Sprint when the Product Owner asks them to add a new high-priority feature that was not in the Sprint Backlog. The team believes they can complete it without jeopardizing the Sprint Goal. According to Scrum, what should the team do?
75A Scrum team's Sprint Review is scheduled for Friday afternoon. The team has completed all but two Product Backlog items. The Product Owner asks the Scrum Master whether the incomplete items should be demonstrated during the Sprint Review. What is the most appropriate guidance the Scrum Master should provide?
76A Scrum Team is struggling with unclear requirements. The Product Owner wants to ensure the team has a shared understanding of a user story before development begins. Which of the following is the most appropriate technique?
77A Scrum team is struggling with its Daily Scrum. The Scrum Master notices that the meeting often runs long, turns into a status report to the Scrum Master, and does not result in a clear plan for the next 24 hours. Which two actions should the Scrum Master take to improve the Daily Scrum? (Choose two.)
78A Scrum Master is coaching a team that is struggling with the Sprint Retrospective. The team often focuses only on what went wrong and leaves the meeting without concrete actions. Which two techniques should the Scrum Master suggest to improve the effectiveness of the retrospective? (Choose two.)
79A Scrum Team is halfway through a two-week Sprint when the Product Owner learns that a competitor has released a similar feature. The Product Owner wants to add several new Product Backlog items to the current Sprint to respond quickly. What should the Scrum Master do?
80A Scrum team is midway through a two-week Sprint when the Product Owner introduces a new high-priority feature request from a key stakeholder. The team has already completed about 40% of the Sprint Backlog. According to Scrum, what should the team do?
81A team using Kanban has a policy that limits work in progress at the 'In Progress' column to three items. Despite this, the team frequently exceeds the limit, and the board shows many items stuck in 'In Progress' while 'Testing' is empty. Which action best addresses the root cause?
82A Kanban team notices that their cumulative flow diagram (CFD) shows a widening band for the 'In Progress' column over several weeks, while the 'Done' band remains relatively flat. What is the most likely interpretation of this pattern?
83A Scrum Team is struggling with its Daily Scrum. Team members give detailed status updates to the Scrum Master, and the meeting often runs 30 minutes. The Scrum Master wants to improve the event. Which action best aligns with Scrum?
84A Scrum team's Sprint Retrospective keeps producing the same three improvement actions every Sprint, and none of them get implemented. The Scrum Master wants the team to actually finish improvements. Which approach best fits Scrum practice?
85A team adopting Kanban wants to visualize its workflow and identify bottlenecks. Which Kanban practice should the team implement first?
86In Extreme Programming (XP), which practice involves a customer representative working closely with the team to define and prioritize features, providing continuous feedback throughout the project?
87A Scrum Team has been delivering increments every Sprint, but the Product Owner complains that the increments do not provide value to users. The Developers argue that they meet the Definition of Done. What should the Scrum Master do first?
88A Scrum Team is preparing for its first Sprint. The Product Owner has a prioritized Product Backlog, and the team is defining its Definition of Done. Which two characteristics are essential for a useful Definition of Done? (Choose two.)
89A team new to Kanban maps its workflow and discovers that work sits in a 'Code Review' column for many days. The team wants to improve flow without changing its process policies yet. Which Kanban practice should the team apply first to expose the problem and drive improvement?
90A Scrum Team's Sprint Review is consistently a one-way presentation where the Product Owner demos completed features to stakeholders. Stakeholder feedback rarely changes the Product Backlog, and the team feels the event adds little value. What should the Scrum Master do?
91A Scrum team is in the middle of a Sprint when a critical production bug is discovered. The Product Owner wants the team to fix it immediately, but the team is concerned about disrupting the Sprint Goal. What is the most appropriate action according to Scrum?
92A Scrum Team is preparing for its Sprint Retrospective. The Scrum Master wants to ensure the event is effective. Which two actions should the Scrum Master take to support a productive retrospective? (Choose two.)
93An agile team is using Extreme Programming (XP). A developer wants to refactor a complex module but is concerned about breaking existing functionality. Which XP practice should the developer rely on to safely make changes?
94A Scrum Master is helping a team improve its use of the Definition of Done. The team currently has no shared Definition of Done, and each Developer applies their own quality standard. Which TWO actions best align with Scrum? (Choose two.)
95A Scrum team is halfway through a two-week Sprint when the Product Owner asks the developers to add a new high-value feature immediately. The Sprint Goal is still achievable. What should the developers do?
96An agile team using Scrum has a Definition of Done that requires automated regression tests to pass. A developer argues that a small bug fix should be released without running the full suite because the change is trivial. What is the most appropriate response?
Deep-dive questions
The most-searched questions in this domain — detailed explanations, worked examples, full answer breakdowns.
Match each scenario symptom to the correct Agile mechanic: WIP limits for Kanban bottlenecks, the Sprint Retrospective for process improvement, velocity divided into remaining points for release forecasting, and backlog reprioritization plus short iterations for changing requirements. The key skill is selecting the single best-fitting practice, not the most familiar one.
The Courseiva CAPM question bank contains 96 questions in the Agile Frameworks and Methodologies domain, covering the 20% of the exam attributed to this domain in the official PMI blueprint. Click any question to see the full explanation and answer breakdown.
Start with a 10-question focused session to identify your baseline accuracy in this domain. Read every explanation — even for questions you answer correctly — to understand the reasoning. Once you score consistently above 80%, move to a 20–30 question session to confirm depth before moving to the next domain.
Yes — the session launcher on this page draws questions exclusively from the Agile Frameworks and Methodologies domain. Choose 10, 20, 30, or 50 questions for a focused session, or click individual questions to review them one by one.
Save your results, see per-domain analytics, and get readiness scores — free, for every certification.
Sign Up FreeFree forever · Every certification included