Courseiva
Agile Frameworks and MethodologieshardMultiple ChoiceObjective-mapped

CAPM Agile Frameworks and Methodologies Practice Question

A distributed agile team has members in three different time zones. They use Scrum with two-week sprints. The daily Scrum is held at 9:00 AM Eastern Time, which is inconvenient for the team members in India (7:30 PM) and Australia (11:00 PM). The team is struggling with communication and frequently misses the daily Scrum. The product owner is not attending anyway, but the development team members from remote locations feel left out. The Scrum Master wants to improve the situation. The team has decided to try alternating the time of the daily Scrum. However, the product owner insists that the team should all be available at a fixed time. The remote developers are becoming disengaged. What should the Scrum Master do?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Rotate the daily Scrum time each sprint to share the inconvenience fairly

The core of the problem is the meeting time. The Scrum Master should advocate for the team and suggest rotating the time to accommodate everyone, ensuring that the whole team can attend. Having two separate daily Scrums would break the team cohesion. Recording the meeting doesn't allow for live interaction. Moving to email updates eliminates the event's purpose.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Replace the daily Scrum with a daily email status update

    Why it's wrong here

    The daily Scrum is a synchronization event; emails lack the interactive inspection and adaptation.

  • Hold two separate daily Scrums: one for each time zone region

    Why it's wrong here

    This would create information silos and harm team cohesion.

  • Enforce the fixed time rigidly and ask remote members to adjust their schedules

    Why it's wrong here

    This would alienate remote team members and reduce engagement.

  • Rotate the daily Scrum time each sprint to share the inconvenience fairly

    Why this is correct

    Rotating times ensures that all team members can occasionally attend during their normal working hours, fostering inclusion.

About these practice questions

Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.