Courseiva
Agile Frameworks and MethodologiesmediumMatchingObjective-mapped

CAPM Agile Frameworks and Methodologies Practice Question

Match each project management process group to its primary purpose.

Drag a concept onto its matching description — or click a concept then click the description.

Concepts
Matches

Define a new project or phase

Establish scope and plan actions

Complete work defined in plan

Track progress and manage changes

Finalize activities and close project

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Initiating: Define a new project or phase and obtain authorization

The five process groups are Initiating, Planning, Executing, Monitoring and Controlling, and Closing. Each has a distinct purpose: Initiating authorizes, Planning defines scope and plan, Executes performs work, M&C tracks and adjusts, Closing formalizes completion.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Initiating: Define a new project or phase and obtain authorization

    Why this is correct

    Initiating involves defining the project and obtaining authorization to start.

  • Planning: Monitor and control project progress

    Why it's wrong here

    Incorrect — monitoring and controlling is a separate process group; Planning focuses on defining scope and objectives.

  • Executing: Complete the work defined in the plan

    Why this is correct

    Executing involves performing the work to satisfy project requirements.

  • Monitoring and Controlling: Establish project scope and objectives

    Why it's wrong here

    Incorrect — establishing scope and objectives is part of Planning; M&C tracks and regulates progress.

  • Closing: Finalize all activities and formally close the project

    Why this is correct

    Closing completes all activities across process groups to close the project.

  • Initiating: Track, review, and regulate project performance

    Why it's wrong here

    Incorrect — that describes Monitoring and Controlling; Initiating authorizes the project.

About these practice questions

One of 487 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.