Sample questions
Certified Associate in Project Management CAPM practice questions
Which TWO of the following are examples of project constraints? (Choose two.)
Project Management Fundamentals and Core ConceptsmediumSee the answer and why each option is right or wrong →A project manager is leading a construction project with a fixed budget and strict deadline. During execution, a key supplier notifies that a critical material will be delayed by t…
In Kanban, the team is experiencing frequent bottlenecks at the testing stage. Which practice should they adopt to improve flow?
A project manager is performing risk response planning for a high-priority risk. The risk has a high probability and high impact. Which response strategy is most appropriate to red…
A project manager is creating the project schedule. The team estimates that the optimistic time for an activity is 10 days, the pessimistic time is 30 days, and the most likely tim…
A project manager is evaluating the impact of a potential risk on project objectives. The risk has a probability of 0.3 and an impact of $50,000. What is the expected monetary valu…
A project manager is developing a project schedule for a software development project using a predictive approach. After identifying activities and sequencing them, what is the NEX…
In a project to implement a new customer relationship management (CRM) system, the business analyst needs to understand the current workflows and identify areas for improvement. Wh…
A project manager is estimating activity durations for a software development project. The team has historical data from similar projects, but the current project involves new tech…
A project manager is developing the WBS for a large construction project. She has identified the major deliverables and decomposed them into work packages. Which of the following B…
During project execution, a key stakeholder requests a change that would add a new feature to the product. The project manager evaluates the impact on scope, schedule, and cost. Ac…
Project Management Fundamentals and Core ConceptsmediumSee the answer and why each option is right or wrong →Drag and drop the steps for managing project communications in the correct order.
Which THREE factors should a business analyst consider when selecting an elicitation technique for a project?
A team using Scrum has a velocity of 30 story points per Sprint. The Product Owner wants to plan for the next release with 150 story points of work remaining. The team is stable. W…
During a requirements validation session, the project sponsor questions whether a particular requirement aligns with the business case. The business analyst recalls that the requir…
A project manager notices that the project's cost performance index (CPI) is 0.85. What does this indicate?
During project execution, a stakeholder requests a new feature that was not in the original scope. The project manager determines that the feature can be accommodated without affec…
A business analyst reviews existing project documentation, process flows, and system manuals to understand the current environment. This technique is called:
An Agile team is experiencing frequent changes in requirements from stakeholders. Which approach best enables the team to adapt while maintaining productivity?
A company transitioning from a waterfall to a Scrum framework wants to ensure continuous improvement. Which Scrum event is specifically designed for inspecting and adapting the pro…
A project manager is leading a software development project. The sponsor has requested a new feature that was not part of the original scope. The project manager assesses that addi…
Project Management Fundamentals and Core ConceptsmediumSee the answer and why each option is right or wrong →A team adopting Kanban wants to visualize its workflow and identify bottlenecks. Which Kanban practice should the team implement first?
A BA is conducting a feasibility study. Which factor is assessed to determine if the project aligns with strategic goals?
Which is an effective way to prioritize user stories in a product backlog?