Question 283 of 503
Predictive Plan-Based MethodologieshardMultiple ChoiceObjective-mapped

CAPM Predictive Plan-Based Methodologies Practice Question

This CAPM practice question tests your understanding of predictive plan-based methodologies. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Exhibit

Refer to the exhibit.

```
Activity | Predecessor | Duration (days)
A        | None        | 5
B        | A           | 3
C        | A           | 4
D        | B, C        | 2
E        | D           | 1
```

Based on the exhibit, what is the critical path duration of the project?

Question 1hardmultiple choice
Read the full NAT/PAT explanation →

Exhibit

Refer to the exhibit.

```
Activity | Predecessor | Duration (days)
A        | None        | 5
B        | A           | 3
C        | A           | 4
D        | B, C        | 2
E        | D           | 1
```

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

12 days

The critical path is the longest path through the project network diagram, determining the shortest possible project duration. By summing the durations along each path, Path A→B→E→G→H has a total duration of 2+3+4+2+1 = 12 days, which is longer than all other paths, making 12 days the correct critical path duration.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 10 days

    Why it's wrong here

    No path has 10 days duration.

  • 11 days

    Why it's wrong here

    This is the duration of path A-B-D-E, which is not the longest.

  • 12 days

    Why this is correct

    Path A-C-D-E is 12 days, the longest path.

    Related concept

    Read the scenario before looking for a memorised answer.

  • 13 days

    Why it's wrong here

    No path has 13 days duration.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often mistakenly sum the durations of all tasks or pick a path that appears longest visually but contains a dependency error, such as ignoring that tasks must be on a continuous sequence without gaps.

Detailed technical explanation

How to think about this question

The critical path method (CPM) calculates the longest path through a network diagram using forward and backward passes to determine early start, early finish, late start, and late finish dates. Any delay on the critical path directly extends the project duration, while non-critical paths have float (slack) that can absorb delays. In real-world projects, identifying the critical path is essential for resource leveling and schedule compression techniques like crashing or fast-tracking.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related CAPM practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free CAPM practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this CAPM question test?

Predictive Plan-Based Methodologies — This question tests Predictive Plan-Based Methodologies — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: 12 days — The critical path is the longest path through the project network diagram, determining the shortest possible project duration. By summing the durations along each path, Path A→B→E→G→H has a total duration of 2+3+4+2+1 = 12 days, which is longer than all other paths, making 12 days the correct critical path duration.

What should I do if I get this CAPM question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.