CAPM Predictive Plan-Based Methodologies Practice Question
This CAPM practice question tests your understanding of predictive plan-based methodologies. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Exhibit
Refer to the exhibit.
```
Activity | Predecessor | Duration (days)
A | None | 5
B | A | 3
C | A | 4
D | B, C | 2
E | D | 1
```
Based on the exhibit, what is the critical path duration of the project?
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
12 days
The critical path is the longest path through the project network diagram, determining the shortest possible project duration. By summing the durations along each path, Path A→B→E→G→H has a total duration of 2+3+4+2+1 = 12 days, which is longer than all other paths, making 12 days the correct critical path duration.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
✗
10 days
Why it's wrong here
No path has 10 days duration.
✗
11 days
Why it's wrong here
This is the duration of path A-B-D-E, which is not the longest.
✓
12 days
Why this is correct
Path A-C-D-E is 12 days, the longest path.
Related concept
Read the scenario before looking for a memorised answer.
✗
13 days
Why it's wrong here
No path has 13 days duration.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates often mistakenly sum the durations of all tasks or pick a path that appears longest visually but contains a dependency error, such as ignoring that tasks must be on a continuous sequence without gaps.
Detailed technical explanation
How to think about this question
The critical path method (CPM) calculates the longest path through a network diagram using forward and backward passes to determine early start, early finish, late start, and late finish dates. Any delay on the critical path directly extends the project duration, while non-critical paths have float (slack) that can absorb delays. In real-world projects, identifying the critical path is essential for resource leveling and schedule compression techniques like crashing or fast-tracking.
KKey Concepts to Remember
Read the scenario before looking for a memorised answer.
Find the constraint that changes the correct option.
Eliminate answers that are true in general but not in this case.
TExam Day Tips
→Watch for words such as best, first, most likely and least administrative effort.
→Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
Predictive Plan-Based Methodologies — This question tests Predictive Plan-Based Methodologies — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: 12 days — The critical path is the longest path through the project network diagram, determining the shortest possible project duration. By summing the durations along each path, Path A→B→E→G→H has a total duration of 2+3+4+2+1 = 12 days, which is longer than all other paths, making 12 days the correct critical path duration.
What should I do if I get this CAPM question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.