Drag steps to the numbered slots on the right, or tap a step then tap a slot.
CAPM Business Analysis Frameworks Practice Question
Drag and drop the steps for conducting a procurement process in the correct order.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Plan Procurement, then Conduct Procurements, then Select Sellers, then Award Contract, then Control Procurements
The correct procurement process sequence according to PMI is: Plan Procurement Management → Conduct Procurements (solicit bids) → Select Sellers (evaluate and choose) → Award Contract (formalize agreement) → Control Procurements (manage and close). This order ensures that each step logically builds on the previous one.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Plan Procurement, then Conduct Procurements, then Select Sellers, then Award Contract, then Control Procurements
Why this is correct
This is the correct order per PMI's procurement management process: plan the approach, solicit responses, evaluate and select sellers, formalize the award, then manage the contract.
- ✗
Conduct Procurements, then Plan Procurement, then Select Sellers, then Award Contract, then Control Procurements
Why it's wrong here
This is incorrect because procurement planning must precede conducting procurements; you cannot solicit bids without a plan.
- ✗
Plan Procurement, then Select Sellers, then Award Contract, then Conduct Procurements, then Control Procurements
Why it's wrong here
This is incorrect because selecting sellers and awarding contracts cannot happen before conducting (soliciting) procurements; you must first receive and evaluate responses.
- ✗
Plan Procurement, then Conduct Procurements, then Award Contract, then Select Sellers, then Control Procurements
Why it's wrong here
This is incorrect because award of contract must follow selection of the seller; you cannot award to an entity that hasn't been selected.
Go deeper
Related to this question
About these practice questions
One of 487 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.