Question 710 of 1,731
PRINCE2 PracticesmediumMultiple ChoiceObjective-mapped

Purpose of the Risk Register in PRINCE2

This PRINCE2F practice question tests your understanding of prince2 practices. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

What is the purpose of the Risk Register?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

To capture and track information about identified risks throughout the project

The Risk Register is a PRINCE2 management product that captures and tracks all identified risks throughout the project lifecycle. It records risk descriptions, probability, impact, proximity, and responses, ensuring risks are actively managed and monitored. This aligns with the PRINCE2 principle of continued business justification by maintaining visibility of threats and opportunities.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • To approve risk budgets

    Why it's wrong here

    Risk budgets are approved by the Board, not recorded in the register.

  • To report progress to stakeholders

    Why it's wrong here

    Progress is reported via Highlight Reports.

  • To capture and track information about identified risks throughout the project

    Why this is correct

    Correct: the Risk Register is used for recording and tracking risks.

    Related concept

    Read the scenario before looking for a memorised answer.

  • To record all decisions made by the Project Board

    Why it's wrong here

    That would be the Issue Register or decision log.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is confusing the Risk Register with other registers or reports, such as the Issue Register or Highlight Report, leading candidates to select options that describe functions of those products instead.

Detailed technical explanation

How to think about this question

The Risk Register is a living document that evolves from the Risk Management Approach and is updated during each risk management step (identify, assess, plan, implement, communicate). It includes fields such as risk ID, category, cause, event, effect, probability, impact, risk score, response actions, and owner. In PRINCE2, the register is reviewed at every management stage to ensure risks are reassessed and responses remain effective, directly supporting the 'manage by stages' principle.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PRINCE2F practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PRINCE2F practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PRINCE2F question test?

PRINCE2 Practices — This question tests PRINCE2 Practices — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: To capture and track information about identified risks throughout the project — The Risk Register is a PRINCE2 management product that captures and tracks all identified risks throughout the project lifecycle. It records risk descriptions, probability, impact, proximity, and responses, ensuring risks are actively managed and monitored. This aligns with the PRINCE2 principle of continued business justification by maintaining visibility of threats and opportunities.

What should I do if I get this PRINCE2F question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. What is the purpose of the Risk Register?

easy
  • A.To list only the project's threats and their impacts
  • B.To document the top 10 risks for the Project Board
  • C.To record and track all identified risks and their responses
  • D.To allocate the risk budget

Why C: The Risk Register is the central repository for recording and tracking all identified risks (both threats and opportunities) throughout the project lifecycle. It includes details such as risk description, probability, impact, proximity, and the planned responses, ensuring that every risk is managed and monitored. Option C is correct because it captures the complete purpose of the Risk Register as defined in PRINCE2.

Keep practising

More PRINCE2F practice questions

Last reviewed: Jul 4, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.