Question 1,466 of 1,731
Project Initiation and StageshardMultiple ChoiceObjective-mapped

PRINCE2F Project Initiation and Stages Practice Question

This PRINCE2F practice question tests your understanding of project initiation and stages. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project is initiating and the Business Case shows a cost-benefit ratio of 1:1.2. The project board is concerned. What should the project manager do?

Question 1hardmultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Provide justification and request approval

The Business Case shows a cost-benefit ratio of 1:1.2, which is positive (benefits exceed costs). The project board's concern does not automatically invalidate the Business Case. According to PRINCE2, the project manager's role during initiation is to provide the board with the justification (the Business Case) and formally request approval to proceed. Option C is correct because the project manager must present the evidence and seek a decision, not unilaterally change scope or cancel.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Reduce scope to lower costs

    Why it's wrong here

    Scope changes require Board approval and may not be necessary.

  • Seek alternative options to improve benefits

    Why it's wrong here

    May be valid, but the immediate action is to provide justification.

  • Provide justification and request approval

    Why this is correct

    The PM should explain why the ratio is acceptable and let the Board decide.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Recommend project cancellation

    Why it's wrong here

    Too drastic; further analysis is needed.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates assume a low cost-benefit ratio (like 1:1.2) automatically means the project should be cancelled or reworked, but PRINCE2 requires the project manager to present the Business Case as-is and let the board decide.

Detailed technical explanation

How to think about this question

In PRINCE2, the Business Case is developed and refined during the Initiating a Project process. The cost-benefit ratio is a key metric, but the project manager does not have authority to change scope or cancel; these are board-level decisions. The project manager's responsibility is to ensure the Business Case is complete, accurate, and presented for approval. A ratio of 1:1.2 means for every unit of cost, 1.2 units of benefit are expected—this is a positive return, so the board's concern might be about risk or confidence, not the ratio itself.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PRINCE2F practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PRINCE2F practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PRINCE2F question test?

Project Initiation and Stages — This question tests Project Initiation and Stages — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Provide justification and request approval — The Business Case shows a cost-benefit ratio of 1:1.2, which is positive (benefits exceed costs). The project board's concern does not automatically invalidate the Business Case. According to PRINCE2, the project manager's role during initiation is to provide the board with the justification (the Business Case) and formally request approval to proceed. Option C is correct because the project manager must present the evidence and seek a decision, not unilaterally change scope or cancel.

What should I do if I get this PRINCE2F question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.