- A
Reduce scope to lower costs
Why wrong: Scope changes require Board approval and may not be necessary.
- B
Seek alternative options to improve benefits
Why wrong: May be valid, but the immediate action is to provide justification.
- C
Provide justification and request approval
The PM should explain why the ratio is acceptable and let the Board decide.
- D
Recommend project cancellation
Why wrong: Too drastic; further analysis is needed.
PRINCE2F Project Initiation and Stages Practice Question
This PRINCE2F practice question tests your understanding of project initiation and stages. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
A project is initiating and the Business Case shows a cost-benefit ratio of 1:1.2. The project board is concerned. What should the project manager do?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Provide justification and request approval
The Business Case shows a cost-benefit ratio of 1:1.2, which is positive (benefits exceed costs). The project board's concern does not automatically invalidate the Business Case. According to PRINCE2, the project manager's role during initiation is to provide the board with the justification (the Business Case) and formally request approval to proceed. Option C is correct because the project manager must present the evidence and seek a decision, not unilaterally change scope or cancel.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Reduce scope to lower costs
Why it's wrong here
Scope changes require Board approval and may not be necessary.
- ✗
Seek alternative options to improve benefits
Why it's wrong here
May be valid, but the immediate action is to provide justification.
- ✓
Provide justification and request approval
Why this is correct
The PM should explain why the ratio is acceptable and let the Board decide.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Recommend project cancellation
Why it's wrong here
Too drastic; further analysis is needed.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates assume a low cost-benefit ratio (like 1:1.2) automatically means the project should be cancelled or reworked, but PRINCE2 requires the project manager to present the Business Case as-is and let the board decide.
Detailed technical explanation
How to think about this question
In PRINCE2, the Business Case is developed and refined during the Initiating a Project process. The cost-benefit ratio is a key metric, but the project manager does not have authority to change scope or cancel; these are board-level decisions. The project manager's responsibility is to ensure the Business Case is complete, accurate, and presented for approval. A ratio of 1:1.2 means for every unit of cost, 1.2 units of benefit are expected—this is a positive return, so the board's concern might be about risk or confidence, not the ratio itself.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Project Initiation and Stages — study guide chapter
Learn the concepts, then practise the questions
- →
Project Initiation and Stages practice questions
Targeted practice on this topic area only
- →
All PRINCE2F questions
1,731 questions across all exam domains
- →
PRINCE2 Foundation study guide
Full concept coverage aligned to exam objectives
- →
PRINCE2F practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PRINCE2F practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Overview of PRINCE2 and Principles practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and Principles.
Business Case and Organizing practice questions
Practise PRINCE2F questions linked to Business Case and Organizing.
Project Initiation and Stages practice questions
Practise PRINCE2F questions linked to Project Initiation and Stages.
Overview of PRINCE2 and the project environment practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and the project environment.
People: organizations, teams, and leadership practice questions
Practise PRINCE2F questions linked to People: organizations, teams, and leadership.
PRINCE2 Practices practice questions
Practise PRINCE2F questions linked to PRINCE2 Practices.
PRINCE2 Processes practice questions
Practise PRINCE2F questions linked to PRINCE2 Processes.
PRINCE2F fundamentals practice questions
Practise PRINCE2F questions linked to PRINCE2F fundamentals.
PRINCE2F scenario practice questions
Practise PRINCE2F questions linked to PRINCE2F scenario.
PRINCE2F troubleshooting practice questions
Practise PRINCE2F questions linked to PRINCE2F troubleshooting.
Practice this exam
Start a free PRINCE2F practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PRINCE2F question test?
Project Initiation and Stages — This question tests Project Initiation and Stages — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Provide justification and request approval — The Business Case shows a cost-benefit ratio of 1:1.2, which is positive (benefits exceed costs). The project board's concern does not automatically invalidate the Business Case. According to PRINCE2, the project manager's role during initiation is to provide the board with the justification (the Business Case) and formally request approval to proceed. Option C is correct because the project manager must present the evidence and seek a decision, not unilaterally change scope or cancel.
What should I do if I get this PRINCE2F question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 11, 2026
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.