Question 1,413 of 1,731
PRINCE2 PracticeshardMultiple SelectObjective-mapped

What Are the Three Types of Issues in PRINCE2?

This PRINCE2F practice question tests your understanding of prince2 practices. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. A key principle to apply: issue. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Which THREE of the following are types of issue defined in PRINCE2?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Request for Change

PRINCE2 defines three types of issues: Request for Change, Off-specification, and Problem/Concern. Therefore, options A, B, and D are correct. Option C is a risk, not an issue, and option E is effectively the same as option A but under a different name; PRINCE2 uses the term 'Request for Change' specifically, so 'Change request' is not a recognized issue type.

Key principle: Issue

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Request for Change

    Why this is correct

    An RFC is a formal proposal for a change.

    Related concept

    Issue

  • Problem/Concern

    Why this is correct

    A problem/concern is any other issue that needs management attention.

    Related concept

    Issue

  • Risk

    Why it's wrong here

    Risk is a separate practice, not an issue type.

  • Off-specification

    Why this is correct

    An Off-spec is a failure to meet a specification.

    Related concept

    Issue

  • Change request

    Why it's wrong here

    The correct term is 'Request for Change'; 'Change request' is not the official PRINCE2 term.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.

Detailed technical explanation

How to think about this question

Treat this as a scenario question. Identify the problem, the constraint, and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Issue
  • Request for Change
  • Off-specification
  • Problem/Concern

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Issue

Real-world example

How this comes up in practice

A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Issue Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Review issue, then practise related PRINCE2F questions on the same topic to reinforce the concept.

Related practice questions

Related PRINCE2F practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PRINCE2F practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PRINCE2F question test?

PRINCE2 Practices — This question tests PRINCE2 Practices — Issue.

What is the correct answer to this question?

The correct answer is: Request for Change — PRINCE2 defines three types of issues: Request for Change, Off-specification, and Problem/Concern. Therefore, options A, B, and D are correct. Option C is a risk, not an issue, and option E is effectively the same as option A but under a different name; PRINCE2 uses the term 'Request for Change' specifically, so 'Change request' is not a recognized issue type.

What should I do if I get this PRINCE2F question wrong?

Review issue, then practise related PRINCE2F questions on the same topic to reinforce the concept.

What is the key concept behind this question?

Issue

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More PRINCE2F practice questions

Last reviewed: Jun 21, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.