- A
The Executive (Senior Responsible Owner)
Why wrong: The Executive owns the Business Case but does not maintain it.
- B
The Project Manager
The Project Manager maintains the Business Case on behalf of the Executive.
- C
The Project Support
Why wrong: Project Support provides administrative support but does not maintain the Business Case.
- D
The Senior User
Why wrong: The Senior User represents the users and helps define benefits but does not maintain the Business Case.
Who is Responsible for Maintaining the Business Case in PRINCE2?
This PRINCE2F practice question tests your understanding of prince2 practices. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Who is responsible for maintaining the Business Case throughout the project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
The Project Manager
In PRINCE2, the Project Manager is responsible for maintaining the Business Case throughout the project. This includes monitoring the project's viability against the Business Case, updating it with actual costs and benefits, and escalating any deviations to the Project Board. The Project Manager ensures the Business Case remains valid and aligned with the project's objectives.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
The Executive (Senior Responsible Owner)
Why it's wrong here
The Executive owns the Business Case but does not maintain it.
- ✓
The Project Manager
Why this is correct
The Project Manager maintains the Business Case on behalf of the Executive.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
The Project Support
Why it's wrong here
Project Support provides administrative support but does not maintain the Business Case.
- ✗
The Senior User
Why it's wrong here
The Senior User represents the users and helps define benefits but does not maintain the Business Case.
Common exam traps
Common exam trap: answer the scenario, not the keyword
Candidates often confuse accountability with responsibility, mistakenly assigning the maintenance of the Business Case to the Executive instead of the Project Manager. In PRINCE2, the Executive is accountable for the Business Case, but the Project Manager is responsible for its day-to-day maintenance and monitoring.
Detailed technical explanation
How to think about this question
The Business Case is a living document that must be reviewed and updated at every stage boundary and when any exception is raised. The Project Manager uses the Business Case to guide decision-making, such as whether to continue the project based on cost-benefit analysis. In PRINCE2, the Business Case is formally approved by the Executive, but its ongoing maintenance is delegated to the Project Manager to ensure continuous alignment with project realities.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
PRINCE2 Practices — study guide chapter
Learn the concepts, then practise the questions
- →
PRINCE2 Practices practice questions
Targeted practice on this topic area only
- →
All PRINCE2F questions
1,731 questions across all exam domains
- →
PRINCE2 Foundation study guide
Full concept coverage aligned to exam objectives
- →
PRINCE2F practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PRINCE2F practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Overview of PRINCE2 and Principles practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and Principles.
Business Case and Organizing practice questions
Practise PRINCE2F questions linked to Business Case and Organizing.
Project Initiation and Stages practice questions
Practise PRINCE2F questions linked to Project Initiation and Stages.
Overview of PRINCE2 and the project environment practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and the project environment.
People: organizations, teams, and leadership practice questions
Practise PRINCE2F questions linked to People: organizations, teams, and leadership.
PRINCE2 Practices practice questions
Practise PRINCE2F questions linked to PRINCE2 Practices.
PRINCE2 Processes practice questions
Practise PRINCE2F questions linked to PRINCE2 Processes.
PRINCE2F fundamentals practice questions
Practise PRINCE2F questions linked to PRINCE2F fundamentals.
PRINCE2F scenario practice questions
Practise PRINCE2F questions linked to PRINCE2F scenario.
PRINCE2F troubleshooting practice questions
Practise PRINCE2F questions linked to PRINCE2F troubleshooting.
Practice this exam
Start a free PRINCE2F practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PRINCE2F question test?
PRINCE2 Practices — This question tests PRINCE2 Practices — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: The Project Manager — In PRINCE2, the Project Manager is responsible for maintaining the Business Case throughout the project. This includes monitoring the project's viability against the Business Case, updating it with actual costs and benefits, and escalating any deviations to the Project Board. The Project Manager ensures the Business Case remains valid and aligned with the project's objectives.
What should I do if I get this PRINCE2F question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
8 more ways this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Who is responsible for maintaining the Business Case throughout the project?
easy- A.The Executive
- ✓ B.The Project Manager
- C.The Project Support
- D.The Senior User
Why B: The Project Manager is responsible for maintaining the Business Case throughout the project because they manage day-to-day activities, track progress against the Business Case, and provide updated information to the Executive for approval. PRINCE2 assigns the Project Manager the duty of ensuring the Business Case remains viable by monitoring costs, benefits, and risks, and escalating any deviations. This aligns with the 'continued business justification' principle, where the Project Manager is the custodian of the Business Case's ongoing validity.
Variation 2. Who is responsible for maintaining the Business Case throughout the project?
easy- A.Project Assurance
- B.Senior User
- C.Executive
- ✓ D.Project Manager
Why D: The Project Manager maintains the Business Case under the direction of the Executive. The Executive owns it, but the PM does the updates.
Variation 3. Who is responsible for maintaining the Business Case throughout the project?
easy- A.The Senior User
- B.The Executive (Senior Responsible Owner)
- C.The Project Assurance
- ✓ D.The Project Manager
Why D: The Project Manager is responsible for maintaining the Business Case throughout the project, including updating it at each stage boundary. The Executive owns the Business Case but does not maintain it.
Variation 4. Who is responsible for maintaining the Business Case throughout the project?
easy- A.Senior User
- ✓ B.Project Manager
- C.Executive
- D.Project Support
Why B: The Project Manager is responsible for maintaining the Business Case on a day-to-day basis, while the Executive (Senior Responsible Owner) owns it and is accountable for its viability.
Variation 5. Who is responsible for maintaining the Business Case throughout the project?
easy- ✓ A.Project Manager
- B.Project Assurance
- C.Executive
- D.Senior User
Why A: The Project Manager is responsible for maintaining the Business Case on a day-to-day basis, while the Executive (SRO) owns it and is ultimately accountable for its justification.
Variation 6. Who is responsible for maintaining the Business Case throughout the project?
easy- ✓ A.Project Manager
- B.Senior Supplier
- C.Executive
- D.Senior User
Why A: The Project Manager is responsible for maintaining the Business Case as part of day-to-day management, while the Executive owns it and approves changes.
Variation 7. Who is responsible for maintaining the Business Case throughout the project?
easy- A.The Senior User
- B.The Project Board
- ✓ C.The Project Manager
- D.The Senior Supplier
Why C: The Project Manager maintains the Business Case, but the Executive (SRO) is the owner and accountable for it. The question asks who maintains it, so option C is correct. The Senior User defines benefits, and the Senior Supplier provides resources.
Variation 8. Who is responsible for maintaining the Business Case throughout the project?
easy- A.The Project Support
- B.The Senior User
- ✓ C.The Project Manager
- D.The Executive (SRO)
Why C: The Project Manager is responsible for maintaining the Business Case, ensuring it remains viable and up to date. The Executive (SRO) owns the Business Case and is accountable for it, but the PM does the day-to-day maintenance.
Keep practising
More PRINCE2F practice questions
- Which TWO of the following statements about the Quality Review technique are correct?
- A project is in its closing stage. The business case shows that all planned benefits have been realized. What should the…
- Which THREE of the following are PRINCE2 principles?
- A project manager is assigned to a project where the executive is often unavailable. Which role can act as a substitute…
- A project is initiating and the Business Case shows a cost-benefit ratio of 1:1.2. The project board is concerned. What…
- Which management product is used to capture lessons during the Initiation Stage?
Last reviewed: Jul 4, 2026
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.