PRINCE2F PRINCE2 Processes Practice Question
Which TWO of the following are outputs of the Starting Up a Project process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Brief
SU produces the Project Brief, initiation Stage Plan, and Daily Log. The PID is produced in IP, and the Benefits Management Approach is also part of IP.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project Initiation Documentation
Why it's wrong here
PID is produced in IP, not SU.
- ✓
Project Brief
Why this is correct
Correct. The Project Brief is a key output of SU.
- ✓
Daily Log
Why this is correct
Correct. The Daily Log is initiated in SU.
- ✗
Benefits Management Approach
Why it's wrong here
The Benefits Management Approach is developed in IP.
- ✗
Stage Plan for the first delivery stage
Why it's wrong here
SU produces the initiation Stage Plan, not the first delivery stage plan.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.