Courseiva
Process — Managing Technical AspectsmediumMultiple ChoiceObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

A critical risk identified in the risk register has occurred. The planned response was to mitigate, but the impact is higher than anticipated. What should the project manager do FIRST?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Implement the planned mitigation response and then reassess the situation

The risk response plan should be executed first, then reassess and update the risk register. PMI recommends implementing the planned response and evaluating its effectiveness.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Develop a new response from scratch because the impact changed

    Why it's wrong here

    Developing a new response from scratch is premature and inefficient when a pre-defined mitigation plan already exists for a critical risk. The project team has invested time in planning these responses, and the first course of action is always to execute the established strategy. New responses are only developed if the existing plan proves ineffective or the situation significantly deviates from the original assessment *after* initial implementation.

  • Update the risk register and ignore the planned response

    Why it's wrong here

    Merely updating the risk register and ignoring the planned response is a passive and irresponsible approach to risk management. The purpose of proactive risk planning is to have a ready strategy for immediate execution when a risk materializes, not just to document its occurrence. Failing to implement the agreed-upon response negates all prior planning efforts and leaves the project vulnerable to unmitigated impacts.

  • Implement the planned mitigation response and then reassess the situation

    Why this is correct

    When a critical risk materializes, the immediate and most appropriate action is to execute the pre-defined mitigation response documented in the risk register. This proactive step is crucial for minimizing negative impacts and stabilizing the situation according to the established plan. Following the implementation, a reassessment is necessary to evaluate the effectiveness of the response and determine if further actions, such as developing new strategies or escalating, are required.

  • Escalate the risk to the project sponsor immediately

    Why it's wrong here

    Immediately escalating the risk to the project sponsor without first attempting to implement the planned response is generally inappropriate and bypasses the project manager's responsibility. The project manager is expected to manage risks within their authority and execute agreed-upon plans to demonstrate control. Escalation becomes necessary only if the planned response is insufficient, exceeds the PM's authority, or the impact is greater than anticipated *after* initial mitigation efforts.

About these practice questions

One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PMP

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. You are managing a project that is currently in the execution phase. A risk event that was identified and included in the risk register has occurred. The planned response is to mitigate the risk. Which TWO documents should you update to reflect the occurrence and response? (Choose two.)

easy
  • A.Stakeholder engagement plan
  • B.Risk register
  • C.Lessons learned register
  • D.Project schedule
  • E.Cost baseline

Why B: The risk register is updated to document the occurrence of the risk and the response taken. The lessons learned register is updated to capture knowledge about the risk response for future projects. The stakeholder engagement plan is not updated for risk occurrences; the project schedule is only updated if the risk response impacts schedule activities; the cost baseline is only updated if the response impacts the budget. Therefore, options B and C are correct.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.