Courseiva

PMP Practice Question: Business Environment: strategy and project benefits

A project manager is leading a construction project. During execution, a new environmental regulation is enacted that directly affects the project's waste disposal process. What should the project manager do first?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Analyze the impact of the regulation on the project's scope, schedule, and budget.

The correct first step when a new regulation impacts the project is to analyze its effect on scope, schedule, budget, and quality. This aligns with the PMBOK's process of monitoring and controlling and also with regulatory compliance. After analysis, the appropriate change control process should be followed if changes are needed. Option A is premature because analysis should precede any changes. Option B may be too drastic without understanding the impact; compliance can often be achieved gradually. Option C is irresponsible as ignoring the regulation could lead to legal issues. Option D is the correct initial response.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Instruct the team to implement a new disposal method without formal approval.

    Why it's wrong here

    Implementing a new disposal method without formal approval bypasses the established change control process, which is critical for managing project baselines. Such an action introduces unauthorized scope changes, potential cost overruns, and schedule delays without proper impact assessment or stakeholder consensus. This approach increases project risk and violates project governance protocols, leading to uncontrolled project execution.

  • Immediately stop all waste disposal activities to ensure compliance.

    Why it's wrong here

    Immediately halting all waste disposal activities is an extreme and potentially disruptive reaction that could severely impact the project's schedule and budget. This action might lead to significant delays, increased costs for temporary storage or alternative solutions, and potential contractual penalties without a thorough assessment of the regulation's specific requirements or the project's ability to adapt. A more measured, analytical approach is required before such drastic steps.

  • Continue as planned since the regulation is new and not yet enforced.

    Why it's wrong here

    Continuing as planned, despite awareness of a new regulation, demonstrates a lack of proactive risk management and can expose the project to significant future liabilities. Even if not immediately enforced, new regulations often have compliance deadlines or grace periods, and ignoring them can result in costly last-minute adjustments, fines, legal challenges, or reputational damage once enforcement begins. A PMP must anticipate and plan for regulatory changes proactively.

  • Analyze the impact of the regulation on the project's scope, schedule, and budget.

    Why this is correct

    Analyzing the impact of the new regulation on the project's scope, schedule, and budget is the most appropriate and professional first step. This systematic assessment allows the project manager to understand the specific requirements, evaluate potential changes to work packages, estimate the financial and temporal implications, and identify necessary adjustments to project baselines. This proactive analysis forms the basis for informed decision-making and proper change management.

About these practice questions

Courseiva writes every PMP question from scratch — 800 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.