During the execution phase of a road construction project, the team discovers an unmarked underground utility line that was not shown on any plans. Working near it poses a safety risk, and the project must halt until the utility is identified and mapped. The risk register did not include this specific risk. What should the project manager do FIRST?

⚠ Common exam trap

The trap here is that candidates may prioritize updating the risk register or submitting a change request (options C or D) as the 'first' step, but the PMP exam emphasizes that safety and immediate risk response take precedence over documentation or schedule adjustments.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Stop work in the area and engage a utility locating service to identify the line

The immediate priority is to ensure safety by stopping work in the affected area and engaging a utility locating service to identify the unmarked underground utility line. This aligns with the PMBOK Guide's emphasis on managing unforeseen risks that pose safety hazards, even if they are not in the risk register. The project manager must first assess and mitigate the risk before proceeding with any other actions.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Instruct the team to work carefully around the utility to avoid delays

    Why it's wrong here

    Instructing the team to work carefully around an unidentified utility line is an unacceptable response as it directly compromises safety and fails to mitigate an immediate, severe hazard. This approach disregards the potential for serious injury, fatality, or extensive property damage that could result from striking an unknown underground infrastructure. Project managers have a primary ethical and professional responsibility to ensure a safe working environment, which must always override schedule concerns in such critical situations.

  • Stop work in the area and engage a utility locating service to identify the line

    Why this is correct

    Stopping work in the immediate area is the paramount first step, prioritizing the safety of all personnel and preventing potential catastrophic damage to the utility or surrounding environment. Subsequently, engaging a professional utility locating service is crucial for accurately identifying the type, depth, and exact location of the line. This systematic approach ensures that all necessary information is gathered to properly assess the risk and formulate an appropriate, safe, and compliant response plan before any further work proceeds.

  • Update the risk register with this new risk and continue work

    Why it's wrong here

    Merely updating the risk register with the presence of an unidentified utility, while a necessary administrative step, is wholly insufficient as an immediate response to an active, unmitigated hazard. This action does not address the imminent danger to the project team or the potential for severe damage and project delays if work continues. The risk register is a planning and monitoring tool, not a substitute for immediate, decisive risk response actions when a threat materializes during execution.

  • Submit a change request to adjust the project schedule

    Why it's wrong here

    Submitting a change request to adjust the project schedule, while potentially necessary later, is not the immediate priority when an unidentified utility line is encountered. This action focuses prematurely on project timeline impacts rather than the critical, immediate need to ensure safety and gather essential information about the hazard. Formal change control processes are typically initiated after immediate safety measures are in place and the full scope of the impact is understood, not as the initial response to an emergent safety issue.

About these practice questions

One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.