You are the project manager for a large IT infrastructure upgrade. An executive stakeholder has been bypassing you and directly assigning tasks to team members. This has caused confusion and rework. What should you do FIRST?

⚠ Common exam trap

Many candidates choose Option D (escalation) because it seems like a formal, safe response, but the PMP exam emphasizes that the PM should first attempt to resolve issues directly with the stakeholder before involving higher authority.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Schedule a meeting with the executive stakeholder to discuss the impact of bypassing the PM and reinforce the communication plan

The first step in resolving unauthorized task assignments is to directly address the executive stakeholder, clarify the negative impact on the project (e.g., rework, resource contention), and reinforce the approved communication plan. This aligns with the PMI principle of managing stakeholder expectations through proactive communication, not escalation or confrontation.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Update the stakeholder engagement plan and communicate the escalation path

    Why it's wrong here

    While maintaining project plans is crucial, immediately updating the stakeholder engagement plan and communicating an escalation path is a reactive, process-heavy response that bypasses direct, proactive communication. The project manager's initial action should prioritize direct engagement with the executive stakeholder to understand their motivations and reinforce established communication protocols, rather than formalizing an escalation route without prior discussion. This approach risks alienating the stakeholder and escalating the situation prematurely without attempting a collaborative resolution.

  • Schedule a meeting with the executive stakeholder to discuss the impact of bypassing the PM and reinforce the communication plan

    Why this is correct

    This is the most appropriate first action as it demonstrates proactive leadership and a commitment to collaborative problem-solving. Directly engaging the executive stakeholder allows the project manager to understand their perspective, explain the adverse impacts of bypassing established communication channels on project control and team morale, and collaboratively reinforce the agreed-upon communication plan. This approach seeks resolution through dialogue and strengthens stakeholder relationships rather than resorting to immediate escalation or confrontation.

  • Instruct the team members to ignore any requests from the executive

    Why it's wrong here

    Instructing team members to ignore requests from an executive stakeholder is highly confrontational and unprofessional, directly undermining organizational hierarchy and potentially damaging critical relationships. This action would create an adversarial environment, erode trust between the project team and executive leadership, and could lead to significant project and organizational repercussions. The project manager's role is to facilitate communication and resolve conflicts, not to create them by isolating stakeholders from the team.

  • Escalate the issue to the project sponsor and request intervention

    Why it's wrong here

    Immediately escalating the issue to the project sponsor without first attempting direct resolution with the executive stakeholder is premature and bypasses the project manager's primary responsibility for stakeholder management. While escalation is a valid tool, it should be reserved for situations where direct communication has failed or is inappropriate. Premature escalation can be perceived as an inability to manage conflict, potentially weakening the project manager's authority and relationship with both the executive and the sponsor.

Visual reference

Client Recursive Resolver Root DNS (13 root servers) TLD DNS (.com, .org, …) Authoritative example.com query IP addr answer

About these practice questions

This PMP question is part of Courseiva's 800-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.