A new government regulation is announced that will impact your project's deliverables. The regulation requires additional compliance testing that was not in the original scope. The project is currently on schedule and within budget. What should you do FIRST?

⚠ Common exam trap

Test-takers frequently confuse urgency (regulatory compliance) with the need for immediate action, forgetting that the PMP process requires a formal change request as the first step, even for mandatory external regulations.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Submit a change request to formally assess and incorporate the new requirements

The PMBOK Guide mandates that any new requirement, especially one imposed by an external regulation, must first be formally documented and assessed through a change request. This ensures the impact on scope, schedule, budget, and quality is evaluated before any action is taken, maintaining control over the project baseline. The regulation introduces additional compliance testing, which is a technical scope change that requires a formal integrated change control process to update the project management plan and technical specifications.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Add the testing tasks to the project schedule and continue

    Why it's wrong here

    Directly adding new tasks to the project schedule without formal assessment and approval bypasses the established change control process. This action constitutes unauthorized scope creep, potentially impacting the project's scope, schedule, and cost baselines without proper evaluation or stakeholder consensus. It violates the project management plan's governance framework, leading to unmanaged risks and potential project failure.

  • Immediately implement the necessary changes to comply with the regulation

    Why it's wrong here

    Implementing changes immediately, even for compliance, circumvents the critical change control process defined in the project management plan. This premature action prevents a thorough analysis of the regulation's full impact on project objectives, resources, and existing deliverables. Such an approach introduces significant risks, as unassessed changes can lead to rework, budget overruns, and unintended negative consequences without proper stakeholder review and approval.

  • Inform the sponsor and ask for more budget and time

    Why it's wrong here

    While informing the sponsor and discussing potential budget and time impacts are crucial, doing so *before* formally assessing the new requirements via a change request is premature. This approach skips the necessary structured analysis of alternatives, impacts, and potential solutions that the change control process provides. A formal change request ensures that all implications are thoroughly documented, evaluated, and presented to the sponsor with data-driven recommendations, rather than an immediate, unquantified demand.

  • Submit a change request to formally assess and incorporate the new requirements

    Why this is correct

    Submitting a change request is the correct first step because it initiates the formal change control process, as defined in the project management plan. This structured approach ensures that the new government regulation's impact on project scope, schedule, cost, quality, and risks is thoroughly assessed. It allows for a controlled evaluation of alternatives, stakeholder review, and formal approval before any modifications are incorporated into the project baselines, maintaining project integrity and governance.

About these practice questions

This PMP question is part of Courseiva's 800-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.