Question 860 of 892
Process — Managing Technical AspectshardMultiple ChoiceObjective-mapped

Quick Answer

The answer is to submit a change request to perform rework and update the project management plan accordingly. This is correct because when a quality audit reveals a concrete strength nonconformance, the defect must be formally addressed through the Perform Integrated Change Control process; a corrective action is required to bring the deliverable into compliance, and any rework delay must be documented and approved before implementation. On the PMP exam, this scenario tests your understanding that quality findings always trigger a change request, not immediate rework—even on a tight schedule, bypassing the change control process is a trap. The key memory tip is “Audit → Change Request, Not Action”: after identifying a nonconformance, your next step is always to submit a formal corrective action request, not to start reworking or escalating without following the defined process.

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

You are managing a construction project. During a quality audit, you find that the concrete used in the foundation does not meet the specified strength requirements. The team has already poured the concrete. The project is on a tight schedule, and rework will delay the project by three weeks. What should you do NEXT?

Question 1hardmultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Submit a change request to perform rework and update the project management plan accordingly.

Since the non-conformance has been identified, the next step is to create a corrective action request and follow the change control process to address the issue properly.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Submit a change request to perform rework and update the project management plan accordingly.

    Why this is correct

    This follows the correct process: document the issue, assess impact, and obtain approval for corrective action.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Reinforce the concrete to meet strength requirements without removing it.

    Why it's wrong here

    This may not be technically feasible and bypasses proper quality control processes.

  • Instruct the team to continue work and document the deviation as a lesson learned.

    Why it's wrong here

    Ignoring the quality issue is gold-plating avoidance? It violates quality requirements and could lead to safety issues.

  • Replace the project manager responsible for quality control.

    Why it's wrong here

    Blaming individuals is not a PMI-recommended action; focus on process improvement.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.

Detailed technical explanation

How to think about this question

This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.
  • Use explanations to understand the rule behind the answer.

TExam Day Tips

  • Underline the problem statement mentally.
  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Submit a change request to perform rework and update the project management plan accordingly. — Since the non-conformance has been identified, the next step is to create a corrective action request and follow the change control process to address the issue properly.

What should I do if I get this PMP question wrong?

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 21, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.