- A
Project Manager
The Project Manager is responsible for maintaining the Business Case throughout the project.
- B
Executive
Why wrong: The Executive owns the Business Case but is not responsible for its day-to-day maintenance.
- C
Project Assurance
Why wrong: Project Assurance is responsible for independent oversight, not maintaining the Business Case.
- D
Senior Supplier
Why wrong: The Senior Supplier is responsible for providing resources and expertise, not maintaining the Business Case.
Who Maintains the Business Case in PRINCE2? The Project Manager's Duty
This PRINCE2F practice question tests your understanding of prince2 practices. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Who is responsible for maintaining the Business Case throughout the project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Project Manager
The Project Manager is responsible for maintaining the Business Case throughout the project because PRINCE2 requires the Business Case to be a living document that is updated as new information emerges. The Project Manager ensures that the Business Case remains viable by monitoring costs, benefits, risks, and progress against the approved baseline, and by producing regular Highlight Reports and Checkpoint Reports that feed into the ongoing justification. This responsibility is explicitly defined in the PRINCE2 manual under the 'Business Case' management product and the 'Managing a Stage Boundary' process.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Project Manager
Why this is correct
The Project Manager is responsible for maintaining the Business Case throughout the project.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Executive
Why it's wrong here
The Executive owns the Business Case but is not responsible for its day-to-day maintenance.
- ✗
Project Assurance
Why it's wrong here
Project Assurance is responsible for independent oversight, not maintaining the Business Case.
- ✗
Senior Supplier
Why it's wrong here
The Senior Supplier is responsible for providing resources and expertise, not maintaining the Business Case.
Common exam traps
Common exam trap: answer the scenario, not the keyword
PRINCE2 often tests the distinction between accountability (Executive) and responsibility (Project Manager) for the Business Case, leading candidates to mistakenly select the Executive because they confuse ownership with maintenance.
Detailed technical explanation
How to think about this question
In PRINCE2, the Business Case is a dynamic document that must be formally reviewed at each stage boundary (via the 'Managing a Stage Boundary' process) and at the end of the project. The Project Manager uses the 'Business Case' management product to capture updated cost and benefit forecasts, risk assessments, and any changes in the project's justification. A real-world scenario where this matters is when a project encounters a significant cost overrun or a change in market conditions; the Project Manager must update the Business Case to reflect the new reality and then present it to the Project Board for a decision on whether to continue.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
PRINCE2 Practices — study guide chapter
Learn the concepts, then practise the questions
- →
PRINCE2 Practices practice questions
Targeted practice on this topic area only
- →
All PRINCE2F questions
1,731 questions across all exam domains
- →
PRINCE2 Foundation study guide
Full concept coverage aligned to exam objectives
- →
PRINCE2F practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PRINCE2F practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Overview of PRINCE2 and Principles practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and Principles.
Business Case and Organizing practice questions
Practise PRINCE2F questions linked to Business Case and Organizing.
Project Initiation and Stages practice questions
Practise PRINCE2F questions linked to Project Initiation and Stages.
Overview of PRINCE2 and the project environment practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and the project environment.
People: organizations, teams, and leadership practice questions
Practise PRINCE2F questions linked to People: organizations, teams, and leadership.
PRINCE2 Practices practice questions
Practise PRINCE2F questions linked to PRINCE2 Practices.
PRINCE2 Processes practice questions
Practise PRINCE2F questions linked to PRINCE2 Processes.
PRINCE2F fundamentals practice questions
Practise PRINCE2F questions linked to PRINCE2F fundamentals.
PRINCE2F scenario practice questions
Practise PRINCE2F questions linked to PRINCE2F scenario.
PRINCE2F troubleshooting practice questions
Practise PRINCE2F questions linked to PRINCE2F troubleshooting.
Practice this exam
Start a free PRINCE2F practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PRINCE2F question test?
PRINCE2 Practices — This question tests PRINCE2 Practices — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Project Manager — The Project Manager is responsible for maintaining the Business Case throughout the project because PRINCE2 requires the Business Case to be a living document that is updated as new information emerges. The Project Manager ensures that the Business Case remains viable by monitoring costs, benefits, risks, and progress against the approved baseline, and by producing regular Highlight Reports and Checkpoint Reports that feed into the ongoing justification. This responsibility is explicitly defined in the PRINCE2 manual under the 'Business Case' management product and the 'Managing a Stage Boundary' process.
What should I do if I get this PRINCE2F question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
5 more ways this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Who is responsible for maintaining the Business Case throughout the project?
easy- A.Senior User
- ✓ B.Project Manager
- C.Executive
- D.Project Support
Why B: The Project Manager is responsible for maintaining the Business Case throughout the project because PRINCE2 requires the Business Case to be a living document that is reviewed and updated at each stage boundary. The Project Manager ensures that the Business Case remains viable by monitoring costs, benefits, and risks against the approved plan, and escalates any deviations to the Project Board. This responsibility is explicitly assigned to the Project Manager in the PRINCE2 manual for the Business Case management process.
Variation 2. Who is responsible for maintaining the Business Case throughout the project?
easy- A.Senior User
- ✓ B.Project Manager
- C.Project Board
- D.Senior Supplier
Why B: The Project Manager is responsible for maintaining the Business Case throughout the project because PRINCE2 assigns day-to-day management of the Business Case to the Project Manager, who must ensure it remains viable and aligned with the project's progress. The Project Manager updates the Business Case with actual costs, benefits, and risks, and presents it to the Project Board for approval at key decision points. This is defined in PRINCE2's Business Case management approach, where the Project Manager acts as the custodian of the document.
Variation 3. Who is responsible for maintaining the Business Case throughout the project?
easy- A.Executive
- B.Senior User
- C.Project Support
- ✓ D.Project Manager
Why D: The Project Manager is responsible for maintaining the Business Case throughout the project because they manage day-to-day activities, monitor progress against the Business Case, and escalate any deviations to the Project Board. PRINCE2 assigns this operational responsibility to the Project Manager to ensure the Business Case remains viable and aligned with project objectives.
Variation 4. Who is responsible for maintaining the Business Case throughout the project?
easy- A.Project Assurance
- B.Senior User
- ✓ C.Project Manager
- D.Executive
Why C: The Project Manager is responsible for maintaining the Business Case throughout the project because they manage day-to-day activities, monitor progress against the Business Case, and ensure that the project remains viable. PRINCE2 assigns this duty to the Project Manager as part of their ongoing management and reporting responsibilities, not just at initiation.
Variation 5. Who is responsible for maintaining the Business Case throughout the project?
easy- A.The Executive
- ✓ B.The Project Manager
- C.The Project Assurance
- D.The Senior User
Why B: The Project Manager is responsible for maintaining the Business Case throughout the project because they manage day-to-day activities, track progress against the Business Case, and escalate any deviations to the Executive. PRINCE2 assigns this operational responsibility to the Project Manager to ensure continuous alignment with the project's justification.
Keep practising
More PRINCE2F practice questions
- Which TWO of the following statements about the Quality Review technique are correct?
- A project is in its closing stage. The business case shows that all planned benefits have been realized. What should the…
- Which THREE of the following are PRINCE2 principles?
- A project manager is assigned to a project where the executive is often unavailable. Which role can act as a substitute…
- A project is initiating and the Business Case shows a cost-benefit ratio of 1:1.2. The project board is concerned. What…
- Which management product is used to capture lessons during the Initiation Stage?
Last reviewed: Jul 4, 2026
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.