- A
Continued Business Justification: The project must have a valid business justification that is reviewed regularly.
The Continued Business Justification principle ensures the project remains viable by regularly reviewing the business case.
- B
Learn from Experience: Lessons are actively sought and applied throughout the project.
The Learn from Experience principle emphasizes using lessons from previous projects and current experience.
- C
Defined Roles and Responsibilities: Each project has defined roles and responsibilities for all participants.
This principle ensures clear accountability and authority, with roles like Executive, Senior User, etc.
- D
Manage by Stages: The project is planned, supervised, and controlled on a stage-by-stage basis.
Managing by stages allows for control and review at key decision points.
- E
Manage by Exception: The project manager has unlimited authority without any tolerances.
Why wrong: Incorrect — Manage by Exception actually sets tolerances for time, cost, etc., and escalates deviations.
- F
Tailor to Suit the Project Environment: The project must follow a standard approach without adjustment.
Why wrong: Incorrect — the principle Tailor to Suit the Project Environment requires adapting PRINCE2 to the project's context.
PRINCE2 Principles Matching — Descriptions Exercise | PRINCE2 Foundation Explained
This PRINCE2F practice question tests your understanding of overview of prince2 and principles. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Match each PRINCE2 principle to its description.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Continued Business Justification: The project must have a valid business justification that is reviewed regularly.
Only options A, B, C, D correctly match the PRINCE2 principle to its description. Option E is incorrect because 'Manage by Exception' involves setting tolerances for authority, not unlimited authority. Option F is incorrect because 'Tailor to Suit the Project Environment' means adapting the method to the project's context, not following a standard approach without adjustment. The seven PRINCE2 principles are: Continued Business Justification, Learn from Experience, Defined Roles and Responsibilities, Manage by Stages, Manage by Exception, Focus on Products, and Tailor to Suit the Project Environment. Option D describes 'Manage by Stages' correctly, but note that 'Manage by Exception' is a separate principle not accurately described in E.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Continued Business Justification: The project must have a valid business justification that is reviewed regularly.
Why this is correct
The Continued Business Justification principle ensures the project remains viable by regularly reviewing the business case.
Related concept
Read the scenario before looking for a memorised answer.
- ✓
Learn from Experience: Lessons are actively sought and applied throughout the project.
Why this is correct
The Learn from Experience principle emphasizes using lessons from previous projects and current experience.
Related concept
Read the scenario before looking for a memorised answer.
- ✓
Defined Roles and Responsibilities: Each project has defined roles and responsibilities for all participants.
Why this is correct
This principle ensures clear accountability and authority, with roles like Executive, Senior User, etc.
Related concept
Read the scenario before looking for a memorised answer.
- ✓
Manage by Stages: The project is planned, supervised, and controlled on a stage-by-stage basis.
Why this is correct
Managing by stages allows for control and review at key decision points.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Manage by Exception: The project manager has unlimited authority without any tolerances.
Why it's wrong here
Incorrect — Manage by Exception actually sets tolerances for time, cost, etc., and escalates deviations.
- ✗
Tailor to Suit the Project Environment: The project must follow a standard approach without adjustment.
Why it's wrong here
Incorrect — the principle Tailor to Suit the Project Environment requires adapting PRINCE2 to the project's context.
Common exam traps
Common exam trap: answer the scenario, not the keyword
Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.
Detailed technical explanation
How to think about this question
This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
- Use explanations to understand the rule behind the answer.
TExam Day Tips
- Underline the problem statement mentally.
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which PRINCE2F exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.
- →
Overview of PRINCE2 and Principles — study guide chapter
Learn the concepts, then practise the questions
- →
Overview of PRINCE2 and Principles practice questions
Targeted practice on this topic area only
- →
All PRINCE2F questions
1,731 questions across all exam domains
- →
PRINCE2 Foundation study guide
Full concept coverage aligned to exam objectives
- →
PRINCE2F practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PRINCE2F practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Overview of PRINCE2 and Principles practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and Principles.
Business Case and Organizing practice questions
Practise PRINCE2F questions linked to Business Case and Organizing.
Project Initiation and Stages practice questions
Practise PRINCE2F questions linked to Project Initiation and Stages.
Overview of PRINCE2 and the project environment practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and the project environment.
People: organizations, teams, and leadership practice questions
Practise PRINCE2F questions linked to People: organizations, teams, and leadership.
PRINCE2 Practices practice questions
Practise PRINCE2F questions linked to PRINCE2 Practices.
PRINCE2 Processes practice questions
Practise PRINCE2F questions linked to PRINCE2 Processes.
PRINCE2F fundamentals practice questions
Practise PRINCE2F questions linked to PRINCE2F fundamentals.
PRINCE2F scenario practice questions
Practise PRINCE2F questions linked to PRINCE2F scenario.
PRINCE2F troubleshooting practice questions
Practise PRINCE2F questions linked to PRINCE2F troubleshooting.
Practice this exam
Start a free PRINCE2F practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PRINCE2F question test?
Overview of PRINCE2 and Principles — This question tests Overview of PRINCE2 and Principles — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Continued Business Justification: The project must have a valid business justification that is reviewed regularly. — Only options A, B, C, D correctly match the PRINCE2 principle to its description. Option E is incorrect because 'Manage by Exception' involves setting tolerances for authority, not unlimited authority. Option F is incorrect because 'Tailor to Suit the Project Environment' means adapting the method to the project's context, not following a standard approach without adjustment. The seven PRINCE2 principles are: Continued Business Justification, Learn from Experience, Defined Roles and Responsibilities, Manage by Stages, Manage by Exception, Focus on Products, and Tailor to Suit the Project Environment. Option D describes 'Manage by Stages' correctly, but note that 'Manage by Exception' is a separate principle not accurately described in E.
What should I do if I get this PRINCE2F question wrong?
Identify which PRINCE2F exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
1 more ways this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Match each PRINCE2 principle to its description.
medium- ✓ A.Continued Business Justification: The project must remain viable in terms of costs vs benefits.
- ✓ B.Learn from Experience: Lessons are sought and recorded throughout the project.
- ✓ C.Manage by Stages: The project is planned and controlled on a stage-by-stage basis.
- ✓ D.Focus on Products: The project's primary focus is on defining and delivering products.
- E.Continued Business Justification: The project is divided into manageable stages.
- F.Learn from Experience: Management by exception is applied to empower decision-making.
Why A: The correct matches are: Continued Business Justification: project viability; Learn from Experience: lessons logging; Manage by Stages: stage-by-stage planning; Focus on Products: product delivery. Common confusions include swapping stage management with business justification and exception management with learning from experience.
Keep practising
More PRINCE2F practice questions
- Which TWO of the following statements about the Quality Review technique are correct?
- A project is in its closing stage. The business case shows that all planned benefits have been realized. What should the…
- Which THREE of the following are PRINCE2 principles?
- A project manager is assigned to a project where the executive is often unavailable. Which role can act as a substitute…
- A project is initiating and the Business Case shows a cost-benefit ratio of 1:1.2. The project board is concerned. What…
- Which management product is used to capture lessons during the Initiation Stage?
Last reviewed: Jun 11, 2026
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.