- A
Initiation Stage Plan
Correct. The plan for the initiation stage is produced in SU.
- B
Project Brief
Correct. The Project Brief is an output of SU.
- C
Benefits Management Approach
Why wrong: Benefits Management Approach is produced in IP.
- D
Project Initiation Documentation (PID)
Why wrong: PID is output of IP, not SU.
- E
End Stage Report
Why wrong: End Stage Report is output of SB.
Key Outputs of the Starting Up a Project Process
This PRINCE2F practice question tests your understanding of prince2 processes. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Which TWO of the following are outputs of the Starting Up a Project process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Initiation Stage Plan
The Starting Up a Project process is the pre-project phase where the project board is appointed, the project brief is created, and the initiation stage plan is produced. The Initiation Stage Plan (A) is a direct output because it details the activities, resources, and controls needed for the initiation stage itself, enabling the project board to authorize the next process. The Project Brief (B) is also an output as it captures the initial business justification, scope, and approach, forming the basis for the project mandate and subsequent detailed planning.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Initiation Stage Plan
Why this is correct
Correct. The plan for the initiation stage is produced in SU.
Related concept
Read the scenario before looking for a memorised answer.
- ✓
Project Brief
Why this is correct
Correct. The Project Brief is an output of SU.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Benefits Management Approach
Why it's wrong here
Benefits Management Approach is produced in IP.
- ✗
Project Initiation Documentation (PID)
Why it's wrong here
PID is output of IP, not SU.
- ✗
End Stage Report
Why it's wrong here
End Stage Report is output of SB.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates often confuse the Project Brief (output of Starting Up a Project) with the Project Initiation Documentation (PID) (output of Initiating a Project), or mistakenly think the Benefits Management Approach is created early, when it is actually developed during initiation.
Trap categories for this question
Command / output trap
PID is output of IP, not SU.
Detailed technical explanation
How to think about this question
Under PRINCE2, the Starting Up a Project process ensures that the project is viable before committing significant resources; its outputs (Project Brief and Initiation Stage Plan) are reviewed by the project board to decide whether to proceed to initiation. The Project Brief includes the outline business case, project product description, and project approach, while the Initiation Stage Plan covers time, cost, and quality tolerances for the initiation stage. This separation prevents wasted effort on detailed planning for projects that lack a clear business justification or feasibility.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
PRINCE2 Processes — study guide chapter
Learn the concepts, then practise the questions
- →
PRINCE2 Processes practice questions
Targeted practice on this topic area only
- →
All PRINCE2F questions
1,731 questions across all exam domains
- →
PRINCE2 Foundation study guide
Full concept coverage aligned to exam objectives
- →
PRINCE2F practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PRINCE2F practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Overview of PRINCE2 and Principles practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and Principles.
Business Case and Organizing practice questions
Practise PRINCE2F questions linked to Business Case and Organizing.
Project Initiation and Stages practice questions
Practise PRINCE2F questions linked to Project Initiation and Stages.
Overview of PRINCE2 and the project environment practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and the project environment.
People: organizations, teams, and leadership practice questions
Practise PRINCE2F questions linked to People: organizations, teams, and leadership.
PRINCE2 Practices practice questions
Practise PRINCE2F questions linked to PRINCE2 Practices.
PRINCE2 Processes practice questions
Practise PRINCE2F questions linked to PRINCE2 Processes.
PRINCE2F fundamentals practice questions
Practise PRINCE2F questions linked to PRINCE2F fundamentals.
PRINCE2F scenario practice questions
Practise PRINCE2F questions linked to PRINCE2F scenario.
PRINCE2F troubleshooting practice questions
Practise PRINCE2F questions linked to PRINCE2F troubleshooting.
Practice this exam
Start a free PRINCE2F practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PRINCE2F question test?
PRINCE2 Processes — This question tests PRINCE2 Processes — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Initiation Stage Plan — The Starting Up a Project process is the pre-project phase where the project board is appointed, the project brief is created, and the initiation stage plan is produced. The Initiation Stage Plan (A) is a direct output because it details the activities, resources, and controls needed for the initiation stage itself, enabling the project board to authorize the next process. The Project Brief (B) is also an output as it captures the initial business justification, scope, and approach, forming the basis for the project mandate and subsequent detailed planning.
What should I do if I get this PRINCE2F question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
8 more ways this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Which TWO of the following are outputs of the Starting Up a Project process?
medium- A.Project Initiation Documentation
- B.Benefits Management Approach
- ✓ C.Daily Log
- D.End Stage Report
- ✓ E.Project Brief
Why C: SU produces the Project Brief, Daily Log, and Initiation Stage Plan. PID is from IP.
Variation 2. Which TWO of the following are outputs of the Starting Up a Project process?
medium- A.End Project Report
- ✓ B.Project Brief
- C.Project Initiation Documentation
- ✓ D.Initiation Stage Plan
- E.Benefits Management Approach
Why B: SU produces the Project Brief, Stage Plan for initiation, and Daily Log. The PID is produced in IP, and the End Project Report is produced in CP.
Variation 3. Which TWO of the following are outputs of the Starting Up a Project process?
medium- A.Benefits Management Approach
- ✓ B.Project Brief
- C.Project Initiation Documentation
- D.Risk Management Approach
- ✓ E.Daily Log
Why B: The Starting Up a Project process outputs the Project Brief, Daily Log, initiation Stage Plan, and appoints the Executive and Project Manager. The Risk Management Approach is developed later in Initiating a Project.
Variation 4. Which TWO of the following are outputs of the Starting Up a Project process?
medium- A.Project Initiation Documentation
- ✓ B.Project Brief
- ✓ C.Daily Log
- D.Benefits Management Approach
- E.Stage Plan for the first delivery stage
Why B: SU produces the Project Brief, initiation Stage Plan, and Daily Log. The PID is produced in IP, and the Benefits Management Approach is also part of IP.
Variation 5. Which TWO of the following are outputs of the Starting Up a Project process?
medium- A.Project Initiation Documentation
- ✓ B.Daily Log
- ✓ C.Project Brief
- D.End Project Report
- E.Benefits Management Approach
Why B: The Starting Up a Project process produces the Project Brief and the Daily Log as outputs. The Project Brief provides a high-level overview of the project's justification, scope, and approach, while the Daily Log is used to record informal issues, actions, and events during the startup phase. These are distinct from later-stage documents like the Project Initiation Documentation or End Project Report.
Variation 6. Which TWO of the following are outputs of the Starting Up a Project process?
medium- ✓ A.Project Brief
- B.Risk Register
- C.Benefits Management Approach
- ✓ D.Daily Log
- E.Project Initiation Documentation (PID)
Why A: The Starting Up a Project process is the first process in PRINCE2, executed before the project is formally initiated. Its purpose is to ensure that the project has a viable business justification and that the necessary resources are available. The Project Brief is a key output, providing a high-level overview of the project's scope, objectives, and approach. The Daily Log is also an output, used to record informal issues, actions, and events during the project's early stages.
Variation 7. Which TWO of the following are outputs of the Starting Up a Project process?
easy- ✓ A.Initiation Stage Plan
- B.Benefits Management Approach
- ✓ C.Project Brief
- D.End Project Report
- E.Project Initiation Documentation
Why A: The Starting Up a Project process is the first process in PRINCE2, occurring before the project is formally initiated. Its purpose is to ensure that the project has a viable and worthwhile business justification, and that the necessary authorities exist to proceed. The Initiation Stage Plan is a key output because it plans the work required for the Initiation Stage, which is the next step after Starting Up a Project. The Project Brief is also a core output, as it provides a high-level overview of the project's scope, objectives, and approach, which is used to justify proceeding to initiation.
Variation 8. Which TWO of the following are outputs of the Starting Up a Project process?
medium- A.Project Initiation Documentation
- B.End Stage Report
- ✓ C.Project Brief
- D.Benefits Management Approach
- ✓ E.Initiation Stage Plan
Why C: The Starting Up a Project process is the pre-project phase where the project is evaluated for viability before full initiation. Its key outputs include the Project Brief, which outlines the project's scope, objectives, and approach, and the Initiation Stage Plan, which details the work needed to produce the Project Initiation Documentation. These two outputs are formally defined in PRINCE2 as products of this process.
Keep practising
More PRINCE2F practice questions
- Which TWO of the following statements about the Quality Review technique are correct?
- A project is in its closing stage. The business case shows that all planned benefits have been realized. What should the…
- Which THREE of the following are PRINCE2 principles?
- A project manager is assigned to a project where the executive is often unavailable. Which role can act as a substitute…
- A project is initiating and the Business Case shows a cost-benefit ratio of 1:1.2. The project board is concerned. What…
- Which management product is used to capture lessons during the Initiation Stage?
Last reviewed: Jul 4, 2026
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.