- A
Continued Business Justification
Why wrong: This relates to the Business Case.
- B
Manage by Exception
Correct. Escalation of tolerance deviations is management by exception.
- C
Learn from Experience
Why wrong: This relates to lessons learned.
- D
Focus on Products
Why wrong: This relates to product-based planning.
Manage by Exception Principle in PRINCE2
This PRINCE2F practice question tests your understanding of prince2 practices. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Which PRINCE2 principle is being applied when the Project Manager escalates a tolerance deviation to the Project Board?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Manage by Exception
The 'Manage by Exception' principle is applied when the Project Manager escalates a tolerance deviation to the Project Board. This principle delegates decision-making authority to the Project Manager within defined tolerances (e.g., time, cost, quality, scope, risk, and benefit). When a forecast indicates that a tolerance will be exceeded, the Project Manager must escalate the issue to the Project Board, which then decides on corrective action. This ensures that the Project Board only becomes involved when a deviation threatens the project's agreed limits, embodying the 'manage by exception' approach.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Continued Business Justification
Why it's wrong here
This relates to the Business Case.
- ✓
Manage by Exception
Why this is correct
Correct. Escalation of tolerance deviations is management by exception.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Learn from Experience
Why it's wrong here
This relates to lessons learned.
- ✗
Focus on Products
Why it's wrong here
This relates to product-based planning.
Common exam traps
Common exam trap: answer the scenario, not the keyword
Candidates often confuse 'Manage by Exception' with 'Continued Business Justification' — the escalation of a tolerance breach is about exceeding delegated limits, not about the project's ongoing viability.
Detailed technical explanation
How to think about this question
In PRINCE2, tolerances are set for each management level (e.g., team, project, corporate/programme). The Project Manager operates within project-level tolerances delegated by the Project Board. If a tolerance is forecast to be exceeded, the Project Manager must issue an Exception Report and escalate to the Project Board, which then decides whether to approve a new tolerance, change the plan, or take other corrective action. This mechanism prevents micro-management and ensures the Project Board focuses on strategic decisions only when necessary, aligning with the principle of management by exception.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
PRINCE2 Practices — study guide chapter
Learn the concepts, then practise the questions
- →
PRINCE2 Practices practice questions
Targeted practice on this topic area only
- →
All PRINCE2F questions
1,731 questions across all exam domains
- →
PRINCE2 Foundation study guide
Full concept coverage aligned to exam objectives
- →
PRINCE2F practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PRINCE2F practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Overview of PRINCE2 and Principles practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and Principles.
Business Case and Organizing practice questions
Practise PRINCE2F questions linked to Business Case and Organizing.
Project Initiation and Stages practice questions
Practise PRINCE2F questions linked to Project Initiation and Stages.
Overview of PRINCE2 and the project environment practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and the project environment.
People: organizations, teams, and leadership practice questions
Practise PRINCE2F questions linked to People: organizations, teams, and leadership.
PRINCE2 Practices practice questions
Practise PRINCE2F questions linked to PRINCE2 Practices.
PRINCE2 Processes practice questions
Practise PRINCE2F questions linked to PRINCE2 Processes.
PRINCE2F fundamentals practice questions
Practise PRINCE2F questions linked to PRINCE2F fundamentals.
PRINCE2F scenario practice questions
Practise PRINCE2F questions linked to PRINCE2F scenario.
PRINCE2F troubleshooting practice questions
Practise PRINCE2F questions linked to PRINCE2F troubleshooting.
Practice this exam
Start a free PRINCE2F practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PRINCE2F question test?
PRINCE2 Practices — This question tests PRINCE2 Practices — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Manage by Exception — The 'Manage by Exception' principle is applied when the Project Manager escalates a tolerance deviation to the Project Board. This principle delegates decision-making authority to the Project Manager within defined tolerances (e.g., time, cost, quality, scope, risk, and benefit). When a forecast indicates that a tolerance will be exceeded, the Project Manager must escalate the issue to the Project Board, which then decides on corrective action. This ensures that the Project Board only becomes involved when a deviation threatens the project's agreed limits, embodying the 'manage by exception' approach.
What should I do if I get this PRINCE2F question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
3 more ways this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Which PRINCE2 principle is being applied when the Project Manager escalates an issue that is outside the stage tolerance?
medium- A.Manage by stages
- ✓ B.Manage by exception
- C.Tailor to suit the project environment
- D.Continued business justification
Why B: The principle of 'Manage by exception' is applied when the Project Manager escalates an issue that exceeds the stage tolerance. This principle establishes that each management level (e.g., Project Manager, Project Board) has defined tolerances (e.g., time, cost, quality) for their delegated authority; if a forecast or actual deviation goes beyond those tolerances, the issue must be escalated to the next management level for a decision. By escalating the out-of-tolerance issue, the Project Manager is following the exception-based control mechanism that is core to PRINCE2.
Variation 2. Which PRINCE2 principle is being applied when a project uses management by exception?
medium- A.Continued business justification
- ✓ B.Manage by exception
- C.Manage by stages
- D.Focus on products
Why B: Management by exception is a key principle where tolerances are set and escalation occurs only when tolerances are forecast to be exceeded.
Variation 3. Which PRINCE2 principle is applied when a Project Manager escalates a forecast tolerance deviation to the Project Board?
medium- A.Manage by stages
- B.Focus on products
- ✓ C.Manage by exception
- D.Continued business justification
Why C: When a Project Manager forecasts that a tolerance (e.g., cost or time) will be exceeded, they escalate to the Project Board. This is the direct application of the 'Manage by exception' principle, which defines tolerances for each management level and requires escalation only when those tolerances are forecast to be breached, allowing normal management within tolerances without board intervention.
Keep practising
More PRINCE2F practice questions
- Which TWO of the following statements about the Quality Review technique are correct?
- A project is in its closing stage. The business case shows that all planned benefits have been realized. What should the…
- Which THREE of the following are PRINCE2 principles?
- A project manager is assigned to a project where the executive is often unavailable. Which role can act as a substitute…
- A project is initiating and the Business Case shows a cost-benefit ratio of 1:1.2. The project board is concerned. What…
- Which management product is used to capture lessons during the Initiation Stage?
Last reviewed: Jul 4, 2026
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.