- A
Request an Exception Plan before authorizing the next stage
To address the tolerance breach, the Board should request an Exception Plan to adjust future plans.
- B
Revise the project's cost tolerance
Why wrong: The Board could revise project-level tolerance, but this is not the immediate step; an Exception Plan addresses the stage breach.
- C
Close the project immediately
Why wrong: Closing may be an option but is not the only action; the Board should first consider an Exception Plan.
- D
Authorize the next stage as planned
Why wrong: The tolerance has been fully used; continuing without change risks exceeding overall budget.
Exception Plan After Tolerance Breach — Project Board Action | PRINCE2 Foundation Explained
This PRINCE2F practice question tests your understanding of prince2 practices. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
The Project Board is considering whether to authorize the next stage. The current stage has used all its cost tolerance. What should the Project Board do?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Request an Exception Plan before authorizing the next stage
According to PRINCE2, if a stage has exceeded its cost tolerance, the Project Board cannot authorize the next stage without first assessing the situation. The correct action is to request an Exception Plan, which details how to recover from the deviation and bring the project back within tolerance. This ensures the board has a revised forecast and recovery strategy before committing to further expenditure.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Request an Exception Plan before authorizing the next stage
Why this is correct
To address the tolerance breach, the Board should request an Exception Plan to adjust future plans.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Revise the project's cost tolerance
Why it's wrong here
The Board could revise project-level tolerance, but this is not the immediate step; an Exception Plan addresses the stage breach.
- ✗
Close the project immediately
Why it's wrong here
Closing may be an option but is not the only action; the Board should first consider an Exception Plan.
- ✗
Authorize the next stage as planned
Why it's wrong here
The tolerance has been fully used; continuing without change risks exceeding overall budget.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates may assume the board can simply adjust tolerances or proceed as normal, failing to recognize that PRINCE2 mandates an Exception Plan when a stage exceeds its tolerance, not just a simple revision of the budget.
Detailed technical explanation
How to think about this question
In PRINCE2, an Exception Plan is a detailed plan that replaces the current stage plan when a deviation exceeds tolerance. It is produced by the Project Manager and approved by the Project Board. The board uses the Exception Plan to decide whether to continue with revised forecasts, request further changes, or close the project. This mechanism ensures that the board retains control over significant deviations and does not blindly proceed into the next stage.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
PRINCE2 Practices — study guide chapter
Learn the concepts, then practise the questions
- →
PRINCE2 Practices practice questions
Targeted practice on this topic area only
- →
All PRINCE2F questions
1,731 questions across all exam domains
- →
PRINCE2 Foundation study guide
Full concept coverage aligned to exam objectives
- →
PRINCE2F practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PRINCE2F practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Overview of PRINCE2 and Principles practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and Principles.
Business Case and Organizing practice questions
Practise PRINCE2F questions linked to Business Case and Organizing.
Project Initiation and Stages practice questions
Practise PRINCE2F questions linked to Project Initiation and Stages.
Overview of PRINCE2 and the project environment practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and the project environment.
People: organizations, teams, and leadership practice questions
Practise PRINCE2F questions linked to People: organizations, teams, and leadership.
PRINCE2 Practices practice questions
Practise PRINCE2F questions linked to PRINCE2 Practices.
PRINCE2 Processes practice questions
Practise PRINCE2F questions linked to PRINCE2 Processes.
PRINCE2F fundamentals practice questions
Practise PRINCE2F questions linked to PRINCE2F fundamentals.
PRINCE2F scenario practice questions
Practise PRINCE2F questions linked to PRINCE2F scenario.
PRINCE2F troubleshooting practice questions
Practise PRINCE2F questions linked to PRINCE2F troubleshooting.
Practice this exam
Start a free PRINCE2F practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PRINCE2F question test?
PRINCE2 Practices — This question tests PRINCE2 Practices — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Request an Exception Plan before authorizing the next stage — According to PRINCE2, if a stage has exceeded its cost tolerance, the Project Board cannot authorize the next stage without first assessing the situation. The correct action is to request an Exception Plan, which details how to recover from the deviation and bring the project back within tolerance. This ensures the board has a revised forecast and recovery strategy before committing to further expenditure.
What should I do if I get this PRINCE2F question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Keep practising
More PRINCE2F practice questions
- Which TWO of the following statements about the Quality Review technique are correct?
- A project is in its closing stage. The business case shows that all planned benefits have been realized. What should the…
- Which THREE of the following are PRINCE2 principles?
- A project manager is assigned to a project where the executive is often unavailable. Which role can act as a substitute…
- A project is initiating and the Business Case shows a cost-benefit ratio of 1:1.2. The project board is concerned. What…
- Which management product is used to capture lessons during the Initiation Stage?
Last reviewed: Jul 4, 2026
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.