Question 1,397 of 1,731
PRINCE2 PracticesmediumMultiple ChoiceObjective-mapped

Exceeding Cost Tolerance: Project Manager Response

This PRINCE2F practice question tests your understanding of prince2 practices. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Raise an Exception Report to the Project Board and await their direction

In PRINCE2, when a project forecasts exceeding its cost tolerance, the Project Manager must escalate the issue to the Project Board by raising an Exception Report. This is because tolerances are delegated limits; exceeding them requires board-level decision-making. Option B correctly follows the PRINCE2 exception management process, ensuring the board can assess the impact on the Business Case and authorize corrective action.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Continue with the current plan and report the cost overrun in the next Highlight Report

    Why it's wrong here

    Continuing without escalation violates management by exception.

  • Raise an Exception Report to the Project Board and await their direction

    Why this is correct

    This is the correct escalation procedure.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Increase the project budget to absorb the additional cost and continue with the current plan

    Why it's wrong here

    The PM cannot unilaterally increase the budget; that requires Board approval.

  • Close the project immediately as the Business Case is no longer viable

    Why it's wrong here

    A tolerance breach does not automatically mean the Business Case is unviable.

Common exam traps

Common exam trap: answer the scenario, not the keyword

PRINCE2 often tests the misconception that the Project Manager can handle tolerance breaches independently or defer reporting, but PRINCE2 mandates immediate escalation to the Project Board via an Exception Report when tolerances are forecast to be exceeded.

Detailed technical explanation

How to think about this question

Under PRINCE2, cost tolerance is a delegated authority set by the Project Board in the Project Plan. When a forecast breach occurs, the Project Manager must raise an Exception Report detailing the cause, impact, and options (e.g., reduce scope, request additional funds). The board then decides whether to approve a revised plan via an Exception Plan, which replaces the current Stage Plan. This process ensures the Business Case remains viable and aligns with the 'manage by exception' principle, preventing unauthorized escalation of costs.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PRINCE2F practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PRINCE2F practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PRINCE2F question test?

PRINCE2 Practices — This question tests PRINCE2 Practices — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Raise an Exception Report to the Project Board and await their direction — In PRINCE2, when a project forecasts exceeding its cost tolerance, the Project Manager must escalate the issue to the Project Board by raising an Exception Report. This is because tolerances are delegated limits; exceeding them requires board-level decision-making. Option B correctly follows the PRINCE2 exception management process, ensuring the board can assess the impact on the Business Case and authorize corrective action.

What should I do if I get this PRINCE2F question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

3 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

medium
  • A.Continue and report in the next Highlight Report
  • B.Raise an Exception Report to the Project Board
  • C.Close the project
  • D.Increase the cost tolerance and continue

Why B: When tolerance is forecast to be exceeded, the Project Manager must raise an Exception Report to the Project Board.

Variation 2. A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

medium
  • A.Raise an Exception Report to the Project Board and await directions
  • B.Increase the stage budget by using the project's change budget
  • C.Continue with the current plan and report the overrun in the next Highlight Report
  • D.Close the project as the Business Case is no longer viable

Why A: According to PRINCE2's management by exception principle, if a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. The PM cannot exceed tolerance without authorization.

Variation 3. A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

medium
  • A.Close the project immediately as the Business Case is no longer viable
  • B.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
  • C.Raise an Exception Report to the Project Board and await their direction before proceeding
  • D.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report

Why C: In PRINCE2, when a project manager forecasts that stage costs will exceed the stage tolerance, they must escalate the issue to the Project Board by raising an Exception Report. This is because the Project Manager does not have the authority to exceed tolerance levels; the Project Board must decide on corrective actions, such as approving a revised plan or closing the project. Option C correctly follows the PRINCE2 management by exception principle.

Keep practising

More PRINCE2F practice questions

Last reviewed: Jul 4, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.