Courseiva
← Back to CompTIA Project+ PK0-005 questions

Scenario-based practice

Hard Difficulty Questions

Practise CompTIA Project+ PK0-005 practice questions — original exam-style scenarios covering every exam domain, with detailed explanations, wrong-answer analysis, and common exam traps.

20
scenario questions
PK0-005
exam code
CompTIA
vendor

Scenario guide

How to approach hard difficulty questions

These are the questions most candidates get wrong. They require connecting multiple concepts, reading tricky output, or knowing edge-case behaviour that isn't on most study cards. Practising them trains you to operate under uncertainty — a necessary skill on the real exam.

Quick answer

Hard Difficulty Questions questions test whether you can apply the concept in context, not just recognise a definition.

How the topic appears in realistic exam-style scenarios.

Which detail in the question changes the correct answer.

How to eliminate plausible but wrong options.

How to connect the question back to the wider exam objective.

Related practice questions

Related PK0-005 topic practice pages

Scenario questions usually connect to one or more exam topics. Use these links to review the underlying concepts behind the scenario.

Practice set

Practice scenarios

Question 1hardmulti select
Full question →

A project manager is leading an agile project using Scrum. The product owner frequently changes priorities based on customer feedback. Which TWO roles are directly responsible for managing these changes? (Select TWO).

Question 2hardmultiple choice
Full question →

During project execution, the project team is experiencing conflicts and questioning the project manager's authority. According to Tuckman's model, which stage is the team in?

Question 3hardmulti select
Full question →

Which THREE are examples of direct costs in a project? (Select THREE.)

Question 4hardmultiple choice
Full question →

A project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 0.9. Which of the following is true?

Question 5hardmultiple choice
Full question →

A project manager is using a control chart to monitor quality. The data points fall within the control limits but show a run of seven points above the mean. What does this indicate?

Question 6hardmultiple choice
Full question →

A project manager is working on a construction project and needs to calculate the total float for a non-critical path activity. The activity has an early start of day 5, late start of day 10, early finish of day 15, and late finish of day 20. What is the total float?

Question 7hardmulti select
Full question →

A project manager is planning risk responses for identified risks. Which THREE are valid risk response strategies?

Question 8hardmulti select
Full question →

A project manager is leading a construction project. The project sponsor has requested that the project be completed one month earlier than originally planned. Which THREE actions should the project manager take to assess the feasibility of this request? (Choose three.)

Question 9hardmultiple choice
Full question →

A project manager reviews the following risk register: R1 (Vendor delay) has a probability of 0.8 and an impact of 0.6; R2 (Resource shortage) has a probability of 0.6 and an impact of 0.5; R3 (Technical failure) has a probability of 0.6 and an impact of 0.6; R4 (Scope creep) has a probability of 0.7 and an impact of 0.5. Which risk should the project manager prioritize for active monitoring and response?

Network Topology
|Refer to the exhibit.Risk Register (excerpt):
Question 10hardmultiple choice
Full question →

A project has a BAC of $100,000. The earned value is $40,000, actual cost is $50,000, and planned value is $30,000. What is the estimate at completion (EAC) assuming the current cost performance is expected to continue?

Question 11hardmultiple choice
Full question →

A software development project is currently in the execution phase. The project manager has a team of 10 developers and 2 testers. The project is scheduled to be completed in 6 months, with a budget of $500,000. At the end of month 3, the project manager reviews the status and finds that only 40% of the work is complete, whereas 50% was planned. The actual cost incurred is $280,000. The project manager calculates the CPI as 0.71 and the SPI as 0.80. The project sponsor is concerned and asks for a recovery plan. The project manager must decide the best course of action. Which action should the project manager take?

Question 12hardmultiple choice
Full question →

A project manager is using a schedule compression technique that adds resources to critical path activities to shorten the project duration. Which technique is being used, and what is its primary trade-off?

Question 13hardmultiple choice
Full question →

A project manager is working on a project where a new team member is not receiving project updates. The team member reports that they can access the project portal but not the project emails. Based on the exhibit, what is the most likely cause?

Exhibit

Refer to the exhibit.

Command: ping -c 4 10.0.1.15
Output:
PING 10.0.1.15 (10.0.1.15) 56(84) bytes of data.
From 10.0.1.1 icmp_seq=1 Destination Host Unreachable
From 10.0.1.1 icmp_seq=2 Destination Host Unreachable
From 10.0.1.1 icmp_seq=3 Destination Host Unreachable
From 10.0.1.1 icmp_seq=4 Destination Host Unreachable

--- 10.0.1.15 ping statistics ---
4 packets transmitted, 0 received, +4 errors, 100% packet loss, time 3005ms

Command: arp -a
Output:
? (10.0.1.1) at 00:1a:2b:3c:4d:5e [ether] on eth0
? (10.0.1.15) at <incomplete> on eth0
Question 14hardmultiple choice
Full question →

Refer to the exhibit. What is the total float for task C?

Exhibit

Refer to the exhibit.

```
TASK DURATION PREDECESSORS
A    3 days   none
B    2 days   A
C    4 days   A
D    1 day    B, C
E    2 days   D
```
Question 15hardmulti select
Full question →

A project manager is reviewing the communication plan. Which THREE elements must be included to ensure effective project communications? (Choose three.)

Question 16hardmultiple choice
Full question →

A project sponsor is responsible for providing resources and championing the project. Which of the following is also a primary responsibility of the project sponsor?

Question 17hardmultiple choice
Full question →

A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $100,000, actual cost (AC) is $120,000, and planned value (PV) is $90,000. What is the estimate at completion (EAC) if the project will continue to perform at the current cost performance index (CPI)?

Question 18hardmulti select
Full question →

A project manager is developing a communication plan. Which two factors should be considered for each stakeholder? (Select TWO.)

Question 19hardmultiple choice
Full question →

A project manager is assigned to a project that has a high degree of uncertainty and rapidly changing requirements. The project sponsor is concerned about cost overruns and wants a method that allows for frequent delivery of value while adapting to changes. Which project management methodology should the project manager recommend?

Question 20hardmultiple choice
Full question →

A project manager is reviewing the project management plan and notices that an important deliverable's acceptance criteria are missing. The project is currently in the execution phase. What is the best course of action?

These PK0-005 practice questions are part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style PK0-005 questions with detailed explanations, topic-based practice, mock exams, readiness tracking, and study analytics.