During project closure, which THREE documents should be updated or finalized as part of the lessons learned process?
Lessons learned are added to the organization's knowledge base.
Why this answer
Options A, B, and D are correct. Lessons learned are documented in the lessons learned register, updated in the organizational process assets, and often included in the project final report. Option C is not updated during closure; it's an output of the initiating process.
Option E is not a standard PMI document for lessons learned.