Process — Managing Technical AspectsmediumMultiple SelectObjective-mapped

PMP Change Control Process Practice Question

Your IT infrastructure project is being audited for compliance. The auditor finds that several change requests were approved verbally but not documented. The project is in the execution phase. Which TWO actions should you take?

⚠ Common exam trap

Candidates may incorrectly assume that undocumented changes must be reversed, but if the changes were genuinely approved, the proper remedy is retroactive documentation, not reversal.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Update the change control process to require written approval before implementation

Documented approval is required for compliance; updating the change control process to require written approval prevents future documentation gaps. Option C is correct because retroactively documenting the verbally approved changes and obtaining signatures formalizes them and rectifies the compliance issue. Option B is wrong because reversing changes that were properly approved (albeit verbally) would cause unnecessary rework and delays; the issue is documentation, not validity. Option D is wrong because redoing work is not required since the changes were approved; the issue is documentation, not quality. Option E is wrong because stopping all work is excessive; the audit is about documentation and can be resolved without halting the project.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Update the change control process to require written approval before implementation

    Why this is correct

    This action directly addresses the root cause of the audit finding by strengthening the project's change control system. By mandating written approval *before* implementation, the project ensures that all future changes are properly authorized and documented, aligning with compliance requirements and preventing similar issues from arising in subsequent audits. This is a crucial preventative action for long-term project governance and audit readiness.

  • Reverse the undocumented changes and revert to the original baseline

    Why it's wrong here

    Reverting to the original baseline is an unnecessary and wasteful action. The core issue identified by the audit is a lack of proper documentation for approved changes, not that the changes themselves were unauthorized or incorrect. Undoing approved work would incur significant rework costs and schedule delays without resolving the underlying process deficiency in change management.

  • Retroactively document all verbal change requests and obtain signatures

    Why this is correct

    This is a critical remedial action to address the immediate non-compliance identified by the audit. Retroactively documenting all verbally approved changes and securing formal signatures creates the necessary audit trail, demonstrating due diligence and accountability for past modifications. This step ensures that the project can provide evidence of authorized changes, satisfying current audit requirements and validating project expenditures.

  • Request the team to redo the work to ensure it meets requirements

    Why it's wrong here

    Requesting the team to redo the work is inappropriate as the audit did not indicate that the completed work fails to meet requirements or quality standards. The problem lies with the *documentation* of the change approval process, not the technical execution or validity of the work itself. Redoing work would be a significant waste of project resources, time, and budget, without addressing the actual compliance gap.

  • Stop all project work until the audit is resolved

    Why it's wrong here

    Halting all project work is an extreme and disproportionate response to a documentation compliance issue. While the audit is serious, it primarily concerns process adherence and record-keeping, not an immediate threat to project viability or safety. Stopping work would lead to significant schedule delays, increased costs, and potential loss of momentum, without directly contributing to the resolution of the documentation problem.

Visual reference

Client Recursive Resolver Root DNS (13 root servers) TLD DNS (.com, .org, …) Authoritative example.com query IP addr answer

About these practice questions

Courseiva writes every PMP question from scratch — 800 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.