Courseiva
Process — Managing Technical AspectsmediumMultiple ChoiceObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

Your project is halfway through its schedule, and you are performing a variance analysis. You find that the cost performance index (CPI) is 0.85 and the schedule performance index (SPI) is 1.1. What is the MOST likely cause of this situation?

⚠ Common exam trap

The trap here is that candidates see SPI > 1.0 and CPI < 1.0 and incorrectly assume a data error, rather than recognizing the realistic project management trade-off of overtime causing cost overruns while accelerating schedule.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The team is working overtime to meet deadlines, resulting in higher labor costs

A CPI of 0.85 indicates that for every dollar spent, only $0.85 of earned value is being delivered, meaning the project is over budget. An SPI of 1.1 indicates the project is ahead of schedule (10% more work completed than planned). The most likely cause is that the team is working overtime to achieve the schedule gains, which increases labor costs (e.g., overtime pay rates) without a proportional increase in output, driving the cost overrun.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Scope has been reduced without corresponding cost reduction

    Why it's wrong here

    Scope reduction would likely improve CPI and SPI, not this pattern.

  • There is a calculation error in the earned value data

    Why it's wrong here

    Assuming error without evidence is not the most likely cause.

  • The team is working overtime to meet deadlines, resulting in higher labor costs

    Why this is correct

    Overtime can accelerate schedule but increases cost, explaining CPI <1 and SPI >1.

  • The project is under budget and ahead of schedule

    Why it's wrong here

    CPI <1 indicates over budget, not under budget.

About these practice questions

Courseiva writes every PMP question from scratch — 800 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.