Courseiva
Process — Managing Technical AspectsmediumMultiple ChoiceObjective-mapped

Estimate at Completion (EAC) with Typical CPI

Your project is 40% complete, and the earned value analysis shows CPI = 0.85 and SPI = 0.90. The project sponsor is concerned about the cost overrun. The original budget at completion (BAC) is $1,000,000. What is the Estimate at Completion (EAC) using the typical cost performance index (CPI) assumption?

Quick Answer

The answer is $1,176,471. This is correct because the Estimate at Completion (EAC) using the typical CPI assumption is calculated by dividing the Budget at Completion (BAC) by the cumulative CPI, reflecting the expectation that the current cost efficiency will persist for the remainder of the project. On the PMP exam, this formula—EAC = BAC / CPI—tests your ability to apply earned value management when cost variances are considered non-recoverable and typical. A common trap is confusing this with the “atypical” formula (EAC = AC + (BAC – EV)), so remember: if the question says “typical” or “current CPI will continue,” use BAC divided by CPI. For memory, think “Typical = Total divided by Trend,” where the trend is the CPI.

⚠ Common exam trap

It's easy for candidates to confuse the EAC formula using CPI (BAC / CPI) with the formula using SPI (BAC / SPI) or incorrectly multiply BAC by CPI, leading to wrong answers like $1,111,111 or $850,000.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

$1,176,471

The typical CPI assumption means the cost performance to date will continue for the remainder of the project. The formula is EAC = BAC / CPI = $1,000,000 / 0.85 = $1,176,470.59, which rounds to $1,176,471. This assumes the same efficiency (CPI) for the remaining work, reflecting the current cost overrun trend.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • $850,000

    Why it's wrong here

    This incorrectly applies the CPI as a multiplier to BAC instead of dividing.

  • $1,000,000

    Why it's wrong here

    This ignores the cost overrun; the project is over budget so EAC should be higher than BAC.

  • $1,111,111

    Why it's wrong here

    This would be BAC / SPI = $1,000,000 / 0.90, but SPI is not used for cost forecasting.

  • $1,176,471

    Why this is correct

    EAC = BAC / CPI = $1,000,000 / 0.85 ≈ $1,176,471, assuming current cost performance is typical.

About these practice questions

Courseiva writes every PMP question from scratch — 800 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PMP

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Your project is 40% complete, and the earned value analysis shows CPI = 0.85 and SPI = 0.90. The project budget is $500,000. What is the Estimate at Completion (EAC) assuming the current cost performance is expected to continue?

medium
  • A.$625,000
  • B.$588,235
  • C.$555,555
  • D.$500,000

Why B: The Estimate at Completion (EAC) when current cost performance is expected to continue is calculated using the formula EAC = BAC / CPI. Given BAC = $500,000 and CPI = 0.85, EAC = $500,000 / 0.85 = $588,235.29, which rounds to $588,235. This assumes the same cost efficiency (CPI) will persist for the remainder of the project, making option B correct.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.