Question 405 of 892
Process — Managing Technical AspectsmediumMultiple ChoiceObjective-mapped

Quick Answer

The answer is $1,176,471. This is correct because the Estimate at Completion (EAC) using the typical CPI assumption is calculated by dividing the Budget at Completion (BAC) by the cumulative CPI, reflecting the expectation that the current cost efficiency will persist for the remainder of the project. On the PMP exam, this formula—EAC = BAC / CPI—tests your ability to apply earned value management when cost variances are considered non-recoverable and typical. A common trap is confusing this with the “atypical” formula (EAC = AC + (BAC – EV)), so remember: if the question says “typical” or “current CPI will continue,” use BAC divided by CPI. For memory, think “Typical = Total divided by Trend,” where the trend is the CPI.

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Your project is 40% complete, and the earned value analysis shows CPI = 0.85 and SPI = 0.90. The project sponsor is concerned about the cost overrun. The original budget at completion (BAC) is $1,000,000. What is the Estimate at Completion (EAC) using the typical cost performance index (CPI) assumption?

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

$1,176,471

When the current cost performance is considered typical and expected to continue, the EAC is calculated as BAC / CPI = $1,000,000 / 0.85 ≈ $1,176,471. This is the most common formula for EAC when variances are expected to persist.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • $850,000

    Why it's wrong here

    This incorrectly applies the CPI as a multiplier to BAC instead of dividing.

  • $1,000,000

    Why it's wrong here

    This ignores the cost overrun; the project is over budget so EAC should be higher than BAC.

  • $1,111,111

    Why it's wrong here

    This would be BAC / SPI = $1,000,000 / 0.90, but SPI is not used for cost forecasting.

  • $1,176,471

    Why this is correct

    EAC = BAC / CPI = $1,000,000 / 0.85 ≈ $1,176,471, assuming current cost performance is typical.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.

Detailed technical explanation

How to think about this question

This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.
  • Use explanations to understand the rule behind the answer.

TExam Day Tips

  • Underline the problem statement mentally.
  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: $1,176,471 — When the current cost performance is considered typical and expected to continue, the EAC is calculated as BAC / CPI = $1,000,000 / 0.85 ≈ $1,176,471. This is the most common formula for EAC when variances are expected to persist.

What should I do if I get this PMP question wrong?

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more ways this is tested on PMP

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Your project is 40% complete, and the earned value analysis shows CPI = 0.85 and SPI = 0.90. The project budget is $500,000. What is the Estimate at Completion (EAC) assuming the current cost performance is expected to continue?

medium
  • A.$625,000
  • B.$588,235
  • C.$555,555
  • D.$500,000

Why B: When current cost performance is expected to continue, EAC = BAC/CPI. BAC = $500,000, CPI = 0.85, so EAC = $500,000 / 0.85 ≈ $588,235.

Last reviewed: Jun 21, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.