Courseiva
Process — Managing Technical AspectsmediumDrag & DropObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

Order the steps for creating a Work Breakdown Structure (WBS).

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4
5Step 5

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Identify deliverables, then Decompose deliverables, then Assign codes, then Verify decomposition, then Create WBS dictionary

The WBS process starts with identifying deliverables, decomposing them, coding, verifying, and documenting in the dictionary.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Identify deliverables, then Decompose deliverables, then Assign codes, then Verify decomposition, then Create WBS dictionary

    Why this is correct

    This is the correct order because the WBS process begins with identifying the key deliverables, then breaking them down into work packages, assigning unique codes for tracking, verifying that the decomposition is complete and consistent, and finally documenting everything in the WBS dictionary.

  • Decompose deliverables, then Identify deliverables, then Assign codes, then Verify decomposition, then Create WBS dictionary

    Why it's wrong here

    The fundamental principle of WBS creation requires a clear understanding of what needs to be delivered before breaking it down. Attempting to decompose deliverables prior to their identification from the project scope statement or requirements documents is illogical and would lead to an incomplete or inaccurate WBS. Deliverables must first be defined and confirmed as the foundational elements.

  • Identify deliverables, then Assign codes, then Decompose deliverables, then Verify decomposition, then Create WBS dictionary

    Why it's wrong here

    Assigning WBS codes prematurely, before the decomposition process is complete, is inefficient and incorrect. WBS codes are hierarchical identifiers applied to work packages and control accounts, which are the outputs of the decomposition process. You must first break down the deliverables into manageable components before assigning unique, structured codes for tracking and management.

  • Identify deliverables, then Decompose deliverables, then Verify decomposition, then Assign codes, then Create WBS dictionary

    Why it's wrong here

    Verifying the decomposition before assigning WBS codes is out of sequence. WBS codes provide a structured, hierarchical framework that is crucial for effectively verifying the completeness, consistency, and logical flow of the decomposed work. The codes facilitate traceability and ensure that all elements are properly accounted for within the WBS structure before final validation.

About these practice questions

One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.