- A
Conduct a retrospective to identify impediments and improvement actions.
Retrospectives are designed to inspect and adapt the process.
- B
Ask the team to work overtime to catch up on velocity.
Why wrong: This can increase burnout and lower morale further.
- C
Replace the underperforming team members with new resources.
Why wrong: This is drastic and may not solve the underlying issues.
- D
Increase the sprint length to give the team more time.
Why wrong: Changing sprint length may not address root cause and could delay feedback.
Quick Answer
The answer is to conduct a retrospective to identify impediments and improvement actions. This is correct because an agile velocity drop root cause analysis is best performed through the team’s own inspect-and-adapt ceremony, where systemic issues—such as technical debt, unclear requirements, or process bottlenecks—can be surfaced collaboratively without blame. On the PMP exam, this scenario tests your understanding of servant leadership and agile frameworks, often appearing as a distractor where the product owner’s pressure tempts you to push for more output. The common trap is choosing to escalate or add pressure, which violates agile principles of self-organization and continuous improvement. Remember the memory tip: when velocity drops, don’t sprint faster—retrospect first.
PMP Process — Managing Technical Aspects Practice Question
This PMP practice question tests your understanding of process — managing technical aspects. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Your agile project has been experiencing decreasing velocity over the last three sprints. The team is frustrated and morale is low. The product owner is pressuring for more features. What is the BEST action for the project manager to take?
Clue words in this question
Noticing these words before you look at the options changes how you read each choice.
Clue:
"best"Why it matters: Signals that multiple options may be partially correct. Choose the option that most directly solves the exact problem described, not the one that sounds most complete.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Conduct a retrospective to identify impediments and improvement actions.
The PM should facilitate a retrospective to identify root causes. Option C is correct because it addresses the issue using agile ceremonies. Option A avoids the problem; Option B adds pressure; Option D is reactive.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Conduct a retrospective to identify impediments and improvement actions.
Why this is correct
Retrospectives are designed to inspect and adapt the process.
Clue confirmation
The clue word "best" in the question point toward this answer.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Ask the team to work overtime to catch up on velocity.
Why it's wrong here
This can increase burnout and lower morale further.
- ✗
Replace the underperforming team members with new resources.
Why it's wrong here
This is drastic and may not solve the underlying issues.
- ✗
Increase the sprint length to give the team more time.
Why it's wrong here
Changing sprint length may not address root cause and could delay feedback.
Common exam traps
Common exam trap: answer the scenario, not the keyword
Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.
Detailed technical explanation
How to think about this question
This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
- Use explanations to understand the rule behind the answer.
TExam Day Tips
- Underline the problem statement mentally.
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.
- →
Process — Managing Technical Aspects — study guide chapter
Learn the concepts, then practise the questions
- →
Process — Managing Technical Aspects practice questions
Targeted practice on this topic area only
- →
All PMP questions
892 questions across all exam domains
- →
Project Management Professional PMP study guide
Full concept coverage aligned to exam objectives
- →
PMP practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PMP practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
People — Leading Projects practice questions
Practise PMP questions linked to People — Leading Projects.
Process — Managing Technical Aspects practice questions
Practise PMP questions linked to Process — Managing Technical Aspects.
Business Environment — Strategy and Value practice questions
Practise PMP questions linked to Business Environment — Strategy and Value.
Business Environment: strategy and project benefits practice questions
Practise PMP questions linked to Business Environment: strategy and project benefits.
PMP fundamentals practice questions
Practise PMP questions linked to PMP fundamentals.
PMP scenario practice questions
Practise PMP questions linked to PMP scenario.
PMP troubleshooting practice questions
Practise PMP questions linked to PMP troubleshooting.
Practice this exam
Start a free PMP practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PMP question test?
Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Conduct a retrospective to identify impediments and improvement actions. — The PM should facilitate a retrospective to identify root causes. Option C is correct because it addresses the issue using agile ceremonies. Option A avoids the problem; Option B adds pressure; Option D is reactive.
What should I do if I get this PMP question wrong?
Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.
Are there clue words in this question I should notice?
Yes — watch for: "best". Signals that multiple options may be partially correct. Choose the option that most directly solves the exact problem described, not the one that sounds most complete.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
6 more ways this is tested on PMP
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Your agile team has been experiencing a decrease in velocity over the last three sprints. During the daily standup, team members seem disengaged and mention they are unsure of the sprint goals. As the scrum master, what should you do FIRST?
easy- A.Add more user stories to the backlog to increase team motivation.
- B.Ask the product owner to speak with the team about the importance of the sprint goals.
- ✓ C.Facilitate a meeting with the team to review and clarify the sprint goal and ensure alignment.
- D.Report the velocity drop to senior management and ask for intervention.
Why C: The sprint goal is established during sprint planning. If the team is unsure of the goal, it indicates that sprint planning may not have been effective. The scrum master should facilitate a discussion to clarify the goal and ensure alignment. This is a proactive coaching step.
Variation 2. During an agile project, the team's velocity has dropped for three consecutive sprints. The retrospective revealed that team members are spending too much time on unplanned support tasks. Which THREE actions should the project manager take?
easy- ✓ A.Facilitate a focused retrospective to identify specific root causes
- ✓ B.Work with the product owner to limit unplanned work from stakeholders
- ✓ C.Review the velocity trend and adjust the sprint backlog accordingly
- D.Reduce the sprint length to increase focus and delivery
- E.Require the team to work overtime to regain lost velocity
Why A: Option A is correct because addressing root causes in retrospectives is key. Option B is correct because the product owner should shield the team from interruptions. Option C is correct because analyzing velocity trends helps identify patterns. Option D is wrong because mandatory overtime leads to burnout. Option E is wrong because reducing scope without proper prioritization is not ideal.
Variation 3. In an agile project, the team's velocity has dropped for three consecutive sprints. The daily standup meetings are rushed, and team members often work in silos. What should the project manager do first?
hard- A.Increase the frequency of daily standups to twice per day
- B.Add more team members to increase capacity
- C.Assign a senior developer to monitor individual productivity
- ✓ D.Facilitate a retrospective to identify impediments and propose improvements
Why D: Option B is correct because the retrospective is the appropriate forum for the team to identify and address process issues. Option A is wrong because it doesn't involve the team in problem-solving. Option C is wrong because adding resources may not address the root cause and can disrupt team dynamics. Option D is wrong because micromanaging is not an agile best practice.
Variation 4. Your agile project is experiencing a drop in velocity for the third consecutive sprint. The team reports that they are spending too much time in unplanned meetings and dealing with frequent requirement changes. Which TWO actions should you take to address this?
medium- A.Encourage the team to work overtime to catch up.
- B.Add more team members to increase capacity.
- C.Increase the sprint duration to give the team more time.
- ✓ D.Implement a process to control scope changes during the sprint.
- ✓ E.Limit work-in-progress (WIP) to reduce multitasking.
Why D: Limiting work-in-progress (WIP) can reduce context switching and improve focus. Implementing a change control process for scope changes during a sprint helps stabilize requirements. Both address root causes of velocity drop.
Variation 5. Your agile project has experienced a significant drop in velocity for two consecutive sprints. The team is blaming unclear requirements from the product owner, while the product owner claims the team is not collaborating enough. As the scrum master, which THREE actions should you take to address the situation?
hard- A.Add buffer time to the next sprint to account for uncertainty
- B.Mandate that the team must collaborate more by pairing on all tasks
- ✓ C.Coach the product owner on techniques for refining the product backlog and writing clear user stories
- ✓ D.Coach the team on self-organization and effective collaboration techniques
- ✓ E.Facilitate a retrospective focused on identifying root causes of the velocity drop
Why C: Options A, B, and D are correct. Facilitating a retrospective (A) allows the team to discuss issues openly. Coaching the team on self-organization (B) helps them improve collaboration. Coaching the product owner on backlog refinement (D) addresses the requirements clarity issue. Option C is incorrect because adding buffer contradicts agile principles. Option E is incorrect because mandating collaboration is not effective and violates self-organization.
Variation 6. In an agile project, the team has missed their sprint commitment for the third consecutive sprint. During the retrospective, team members cite unclear requirements and frequent interruptions from stakeholders. As the project manager, what is the BEST action to take?
medium- A.Require the team to commit to fewer story points next sprint
- ✓ B.Work with the product owner to refine user stories and shield the team from external interruptions
- C.Add more developers to the team to increase velocity
- D.Increase the sprint duration to give the team more time
Why B: Option C is correct because the root cause is unclear requirements and interruptions. The PM should help the product owner refine the backlog and manage stakeholder expectations. Option A is wrong because extending sprints doesn't address the root cause. Option B is wrong because it's a team decision, not a PM directive. Option D is wrong because this is a people/process issue, not a technical one.
Last reviewed: Jun 21, 2026
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.