Courseiva
Process — Managing Technical AspectsmediumMultiple SelectObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

You are managing a marketing campaign project. Midway, you discover that the team has been working on additional features requested by the sales director without formal approval. The project is now 10% over budget. Which TWO actions should you take FIRST?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Meet with the sales director to explain the change control process and the consequences

The correct first actions are to document the unauthorized changes and assess their impact (Option E) and to meet with the sales director to explain the change control process and consequences (Option D). Option E is essential to understand the full effect on budget and schedule before any corrective action. Option D addresses the root cause by educating the stakeholder who initiated the unauthorized changes. Option A is incorrect because accepting changes without proper approval violates project governance and may set a bad precedent. Option B is premature; escalation to sponsor should occur only after internal assessment and discussion with the sales director. Option C is not a primary action; finance should be informed after the impact is assessed and a decision is made.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Accept the changes and update the project baseline accordingly

    Why it's wrong here

    Accepting unauthorized changes and retroactively updating the project baseline without formal review and approval through the Integrated Change Control process is a critical deviation from project management best practices. This action undermines the integrity of the baseline, which serves as the approved plan against which project performance is measured. It sets a dangerous precedent, encouraging future unauthorized modifications and diminishing the project manager's authority and control over the project scope, schedule, and budget.

  • Escalate the issue to the project sponsor for a decision

    Why it's wrong here

    Escalating the issue directly to the project sponsor for a decision at this stage is premature and bypasses the project manager's responsibility to first analyze the situation and engage directly with the involved stakeholder. Before escalating, the project manager should assess the impact of the unauthorized changes and attempt to resolve the issue at the lowest appropriate level, which includes communicating with the sales director to understand their actions and explain the proper process. Unnecessary escalation can also burden the sponsor with operational details that should be managed by the project team.

  • Report the budget overrun to the finance department immediately

    Why it's wrong here

    Reporting a budget overrun to the finance department immediately, without first understanding the full scope of the unauthorized changes, their precise impact on the budget and schedule, and the root cause, is a reactive and incomplete approach. The project manager's initial responsibility is to quantify the deviation, assess its implications, and engage with the responsible stakeholder to address the issue and prevent recurrence. Only after this analysis and initial stakeholder engagement should formal reporting to finance occur, providing comprehensive details and proposed corrective actions.

  • Meet with the sales director to explain the change control process and the consequences

    Why this is correct

    Meeting with the sales director is a crucial first step in addressing unauthorized changes, as it directly engages the responsible stakeholder. This interaction allows the project manager to educate the director on the established change control process, emphasize its importance for project success, and clearly articulate the negative consequences of bypassing it, such as budget overruns or schedule delays. This proactive communication aims to prevent future recurrences and reinforce adherence to project governance, fostering better collaboration and understanding of project protocols.

  • Document the unauthorized changes and assess their impact on budget and schedule

    Why this is correct

    Documenting the unauthorized changes is fundamental for maintaining an accurate project record and establishing a clear understanding of what occurred. Simultaneously, assessing their impact on the project's budget, schedule, scope, and quality is critical because it provides the necessary data to inform subsequent decisions and actions. Without a thorough impact analysis, the project manager cannot effectively evaluate the severity of the deviation, propose appropriate corrective actions, or communicate the true status and implications to other stakeholders or the project sponsor.

About these practice questions

One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.